NexGold Mining (NEXG) — Stock Analysis 2026 [3.0]

Gold Precious Metals Company Analysis
CAD

Analysis as of 5 August 2026. NexGold Mining stock analysis. Fundamentals come from NexGold’s interim statements and MD&A to 31 March 2026, its FY2025 audited statements and MD&A, the Goldboro feasibility-study and Goliath prefeasibility-study technical reports, its 2026 management information circular and its August 2026 corporate presentation; market data is the 31 July 2026 TSXV close and will move. Price deck: base gold US$4,000/oz — the representative trailing average on the fixed US$3,000–5,000/oz grid — with every grid price run as a scenario (deep bear US$3,000 / bear US$3,500 / base US$4,000 / bull US$4,500 / deep bull US$5,000); no forecast deck is on record as a cross-check, and no spot price is used. At the C$1.20 close the market is pricing roughly US$1,132/oz gold, held flat over both mine lives. Figures are Canadian dollars (C$) unless marked US$, at US$1 = C$1.4029; refreshed on each annual report and on material events. Rating: ★★★, Average — Undervalued. For information only, prepared with AI assistance — see the disclaimer at the end.

NexGold Mining is a two-project Canadian gold developer: Goldboro in Nova Scotia holds a feasibility study and every key permit, and the Goliath Gold Complex in Ontario holds a prefeasibility study behind it. The thesis in one line: the shares price gold below the US$1,600/oz Goldboro’s own 2022 study used, yet the company still has to raise most of Goldboro’s capital before it can build. Why now: an updated Goldboro feasibility study and an early-works program are slated for 2026, and the financing that follows decides how much of the value stays with today’s shareholders. To screen every listed gold developer on reserves, AISC and life side by side, open the Metal Pilot gold dataset.

1. Snapshot & thesis

NexGold Mining Corp. (TSXV: NEXG; OTC: NXGCF) is a pre-production gold company headquartered in Toronto. By archetype it is a developer; its sector is precious-metal miner (gold). It holds two studied gold projects — Goldboro (Nova Scotia) and the Goliath Gold Complex (the Goliath, Goldlund and Miller deposits, Ontario) — plus the Niblack project in Alaska, the Weebigee-Sandy Lake joint venture in Ontario and exploration ground; Signal Gold (Goldboro) and Blackwolf Copper and Gold (Niblack) were acquired in 2024–25. (AISC = all-in sustaining cost; P&P = proven and probable reserves; M&I = measured and indicated resources; NPV5% = after-tax net present value at 5%; FS / PFS = feasibility / prefeasibility study.)

Figure 1. NexGold in numbers

C$1.20
Share price (TSXV, 31 Jul 2026)
C$307.1 m
Market capitalisation
C$104.5 m
Cash and investments, no debt
2.42 Moz
P&P gold reserves
4.72 Moz
M&I gold resources (as filed)
190 koz/yr
Study output, both projects
US$849/oz
Goldboro AISC (FS, 2021 costs)
C$271.0 m
Goldboro initial capital
C$5.75
NAV per share (Section 7)
C$7.17
Base-case fair value
3.0/5
Quality rating — Average
Undervalued
Valuation read (Section 7)

Figure data: Table 1; NAV per share and fair value per Section 7, rating per Section 9.

Table 1. NexGold in numbers

Metric Value As of
Share price / market capitalisation C$1.20 / C$307.1 m 31 Jul 2026 (TSXV)
Shares — basic pro forma / fully diluted 255.9 m / 363.8 m Aug 2026
Cash and short-term investments / debt C$104.5 m / nil 31 Mar 2026
P&P reserves / M&I resources 2.42 Moz / 4.72 Moz per asset, Table 2
Study output, Goldboro + Goliath 100 + 90 koz/yr FS 2022 / PFS 2023
Goldboro margin at the base deck C$4,388/oz over the study AISC Section 7
Goldboro initial capital / funding gap C$271.0 m / C$178.7 m Section 7
Net loss / operating cash flow C$41.0 m / C$35.9 m used FY2025
NAV per share / P/NAV C$5.75 / 0.21× 5 Aug 2026 (Section 7)
Base-case fair value / implied return C$7.17 / +497.7% 5 Aug 2026 (Section 7)
Quality rating / valuation read 3.0/5 (Average) / Undervalued, implied +497.7% 5 Aug 2026

Source: NexGold Q1 2026 financial statements and MD&A and FY2025 audited statements on SEDAR+; NexGold corporate presentation, August 2026 (share counts); study figures per Table 2; valuation per Section 7.

Thesis in brief. Bull: a debt-free developer with a fully permitted feasibility-stage mine, a second studied project and 4.72 Moz of M&I resources trades at 0.21× a NAV that already charges a C$178.7 million equity raise — and even the deep-bear blend at US$3,000/oz sits above the price. Bear: nothing is built or financed; the 2021–22 study costs will rise in the update, the US$175 million debt letter of intent is non-binding, two royalties already sit on the projects, and the share count has nearly quadrupled since 2024. What tips it: the terms on which Goldboro is financed. The full rating is in Section 9.

How to read this analysis: the statcards and Section 9 carry the verdict; Sections 2–7 carry the evidence.

2. Assets & operations

NexGold produces nothing yet, so its value is two studied mines levered to the gold price; for the market backdrop see the Gold — A Complete Market Guide. Both studies were struck at US$1,600–1,750/oz on 2021–22 costs, against a US$4,000/oz base deck here. This section sets out each project’s study, approvals, encumbrances and plan, then the group profile and the peer set the scorecard uses.

2.1 Portfolio overview

Table 2. Asset portfolio

Asset Country Stage Interest Study output Reserves Life AISC (study) Listing / operator
Goldboro Canada (Nova Scotia) FS (Jan 2022); all key permits; no construction decision 100% 100 koz/yr 1.15 Moz Probable, 2.26 g/t (eff. 15 Dec 2021) 10.9 yr US$849/oz NexGold (TSXV: NEXG), operator
Goliath Gold Complex Canada (Ontario) PFS (Feb 2023); federal EA 2019 100% 90 koz/yr 1,267 koz P&P, 1.30 g/t (PFS, 22 Feb 2023) ~13 yr US$1,072/oz NexGold (TSXV: NEXG), operator
Niblack · Weebigee-Sandy Lake JV · exploration USA (Alaska) · Canada (Ontario) Exploration; no study 100% / JV — none — — NexGold (TSXV: NEXG)

Source: NexGold Q1 2026 MD&A (study summaries, reserve statements, permits) and FY2024 MD&A (Goliath holding); reserves under NI 43-101, Goldboro Probable only.

Concentration. Goldboro carries 52.7% of the C$2,282.8 million enterprise NAV in Section 7, Goliath 26.6% and the resource-conversion tier 20.7%. Value rests on two Canadian projects, and the first one has to be financed before the second is built. Neither project has a construction decision and neither study has been refreshed since 2023, so the NAV is a study NAV risked for stage — 0.60× at Goldboro, 0.40× at Goliath.

2.2 NAV and resource split

NexGold has no revenue, so the two splits are where the risked value sits and where the ounces sit.

Figure 2. Enterprise NAV by component, base case (C$m)

Goldboro (risked 0.60×)
Goliath (risked 0.40×)
Resource conversion
C$1,203.5 m · 52.7%
C$607.1 m · 26.6%
C$472.2 m · 20.7%
Share of enterprise NAV C$2,282.8 m, US$4,000/oz, 5% real

Figure data: this analysis, Table 11.

Figure 3. M&I gold resources by project (Moz)

Goldboro
Goliath Gold Complex
2.58 Moz · 54.7%
2.14 Moz · 45.3%
Share of 4.72 Moz M&I as filed (Goldboro inclusive of reserves; Goliath basis not stated)

Figure data: Goldboro 2,581,000 oz (eff. 15 Nov 2021) and Goliath Complex 2,138,600 oz (sum of the three deposits) per the Q1 2026 MD&A; Niblack is not shown.

2.3 Goldboro, Nova Scotia

Goldboro, in Guysborough County, is 100% owned and operated by NexGold. The January 2022 FS plans a 10.9-year open pit at 100 koz/yr, a 2.26 g/t mill feed, 95.8% recovery and an 8.0:1 strip, for an after-tax NPV5% of C$328 million, a 25.5% IRR and a 2.9-year payback at US$1,600/oz and US$1 = C$1.25. Initial capital is C$271.0 million, sustaining C$63.1 million and reclamation C$50.3 million; cash costs are US$773/oz and AISC US$849/oz. The Probable reserve is 15,798,900 t at 2.26 g/t for 1,150,200 oz (NI 43-101, effective 15 December 2021), inside an M&I resource of 2,581,000 oz at 3.72 g/t, inclusive of reserves, of which 1,159,000 oz is underground; a further 484,000 oz is Inferred. The underground ounces sit outside the open-pit reserve, which is why Section 7’s conversion tier carries Goldboro value beyond the 10.9-year plan.

Approvals in hand: the Benefits Agreement with the Assembly of Nova Scotia Mi’kmaw Chiefs (12 December 2024), the Crown Land Lease and Licence (May 2025), the MDMER Schedule 2 amendment for the tailings facility (announced 8 July 2025) and the Fisheries Act Authorization (31 October 2025) — all key permits for construction and operation. Outstanding: a construction decision and its financing. Encumbrances: Appian’s 2.9% NSR, sold on 29 September 2025 for C$33.4 million; the Nebari 0.6% NSR was bought back the same day for US$6.9 million. On the surrounding licences sit a 1.0% royalty capped at $1,000,000 and a 2% gross royalty on sixteen licences west of the deposit. An early-works program is planned for H2 2026; first production and the ramp are not guided. Asset risk: the study basis is dated, and an FS and resource update is under way.

2.4 Goliath Gold Complex, Ontario

Goliath, in the Kenora Mining Division, is 100% held and operated by NexGold across the Goliath, Goldlund and Miller deposits. The February 2023 PFS plans 90 koz/yr (128 koz in the peak year) at a 1.30 g/t head grade and 92.8% recovery, 1,175 koz over the life, for a post-tax NPV5% of C$336 million, a 25.4% IRR and a 2.8-year payback at US$1,750/oz gold and US$21/oz silver. Initial capital is C$335 million, sustaining C$198 million, and closure C$29 million less C$10 million of salvage, all at US$1 = C$1.3333 (USD:CAD 0.75); cash costs are US$935/oz and AISC US$1,072/oz (US$1,008/oz in the first five years). The P&P reserve is 1,267 koz in 30,319 kt at 1.30 g/t (the MD&A rounds it to 1.3 Moz) inside 2,138,600 oz of M&I: Goliath open pit 9.5 Mt at 0.83 g/t, Goliath underground 3.8 Mt at 3.03 g/t, Goldlund 16.3 Mt at 1.19 g/t and Miller 0.7 Mt at 1.03 g/t. Sprott holds a 2.2% NSR (sold 11 April 2022 for C$25.2 million), halving after 1.5 Moz, with US$500,000 quarterly minimum payments until the earlier of 31 December 2027 and commercial production; beneath it, $105,000 a year is payable on 13 of the 25 patented claims. The federal EA decision came in 2019; Goliath is the second build, with optimization studies under way. Asset risk: a PFS priced on Q3 2022 costs without an inflation allowance.

2.5 Other assets

Niblack (Alaska), the Weebigee-Sandy Lake joint venture and the exploration properties carry no study in the source set; they are named as optionality and not valued (Section 7.2).

2.6 Study production, reserves & costs

The group’s plan is the two studies: 190 koz/yr once both run, on 2.42 Moz of P&P. Neither is guidance, and both cost bases predate the update. Goldboro’s plan recovers about 1,090 koz (100 koz/yr over 10.9 years) and Goliath’s 1,175 koz — about 2.27 Moz in all; the M&I beyond both plans is the conversion runway.

Figure 4. Study gold production by project (koz/yr)

Study output (koz Au/yr)
200
150
100
50
0
100
90
128
190
Goldboro
FS average
Goliath
PFS average
Goliath
PFS peak year
Both
average
Study basis — not production guidance

Figure data: Goldboro FS and Goliath PFS summaries in the Q1 2026 MD&A.

2.7 Peer positioning

NexGold is scored against three listed Canadian gold peers, each on its own study basis: Artemis Gold (TSXV: ARTG), Skeena Resources (TSX: SKE) and Osisko Development (TSXV: ODV). Artemis poured its first gold and silver doré at Blackwater on 29 January 2025 and targeted commercial production for Q2 2025, so by the as-of date it is a new producer; Skeena and Osisko Development are compared on their studies.

Table 3. Peer positioning — study quality metrics

Company Listing Flagship Output (koz Au/yr) AISC (study deck) P&P reserve Life
NexGold Mining TSXV: NEXG Goldboro (FS) + Goliath (PFS) 100 + 90 US$849 (US$1,600) / US$1,072 (US$1,750) 1.15 Moz at 2.26 g/t + 1.27 Moz at 1.30 g/t 10.9 / ~13 yr
Artemis Gold TSXV: ARTG Blackwater, single asset; 6 → 15 → 25 Mtpa 438 US$781 (US$1,800) 8.0 Moz at 0.75 g/t 17 yr
Skeena Resources TSX: SKE Eskay Creek, single asset; development since Dec 2024 228 (320 AuEq) US$687 AuEq co-product (US$1,800) 3.34 Moz at 2.6 g/t 12 yr
Osisko Development TSXV: ODV Cariboo, single asset; 5.0% NSR 191.8 US$1,157 incl. royalties (US$2,400) 2.07 Moz at 3.62 g/t 10 yr

Source: Artemis Gold FY2024 AIF, Skeena FY2025 AIF and Q1 2026 MD&A, Osisko Development FY2025 AIF; NexGold per Table 2. Quality metrics only — no multiples.

NexGold sits at the small end: its combined 190 koz/yr is level with Cariboo’s single mine and below Eskay Creek and Blackwater, its reserve grades sit between Blackwater’s 0.75 g/t and Cariboo’s 3.62 g/t, and its study AISC is mid-field — on the oldest cost base and the lowest price deck of the four.

3. Financials & balance sheet

NexGold has no revenue, so its financials are a spending, cash and dilution record. The FY2025 net loss was C$41.0 million and operations used C$35.9 million of cash, against C$19.6 million and C$15.0 million in FY2024; Q1 2026 added a C$11.4 million loss, C$8.8 million of it exploration and evaluation. For the metrics used here, see the Financial Metrics for Commodity Investing guide.

Table 4. Financial summary (developer basis, C$m)

Metric FY2021 FY2022 FY2023 FY2024 FY2025 Q1 2026
Revenue nil nil nil nil nil nil
Net loss (15.9) (20.3) (13.4) (19.6) (41.0) (11.4)
Loss per share (C$, post-consolidation) (0.51) (0.59) (0.37) (0.30) (0.24) (0.05)
Operating cash flow (17.8) (17.8) (11.3) (15.0) (35.9) (8.6)
Capex (sustaining / growth) n/d n/d n/d n/d n/d n/d
Cash and equivalents 10.1 16.0 9.4 16.4 87.7 84.5
Debt (current + long-term) 5.4 7.1 0.3 16.3 nil nil
Weighted shares (m) 31.3 34.5 36.6 65.4 168.6 247.9 (period end)
Dividend per share nil nil nil nil nil nil

Source: NexGold FY2025, FY2024 and FY2023 audited financial statements, Treasury Metals’ FY2022 audited statements and the Q1 2026 interim statements; FY2021–23 are Treasury Metals’ statements. Notes: 1. FY2021 is the comparative column of Treasury Metals’ FY2022 audited statements. 2. Capex and FCF are n/d in the extract; ND/EBITDA is not meaningful with no EBITDA. 3. Per-share and share rows are on the post-consolidation basis (one new share for four, 9 July 2024): FY2023 as restated in the FY2024 statements; FY2021 and FY2022 are the filed losses over the filed weighted shares ÷ 4. 4. Debt is current plus long-term on the latest basis; FY2024 is the Nebari facility, and FY2023 is as restated in the FY2024 statements (C$0.3 m; C$7.6 m as first reported).

Cost deck. No cost guidance exists before production. The study bases are Goldboro’s US$773/oz cash cost and US$849/oz AISC (C$67.05/t milled, 2021 costs, US$1 = C$1.25) and Goliath’s US$935/oz and US$1,072/oz (Q3 2022 costs, no inflation allowance). Price-linked costs are the Appian 2.9% and Sprott 2.2% NSRs. Tax is modelled at the statutory rates: 29% at Goldboro (federal 15% + Nova Scotia 14%) and 33.85% at Goliath (federal 15% + Ontario 11.5%, with the 10% Ontario mining tax deductible). Tax pools: C$66.3 million of non-capital losses.

Net debt and liquidity. NexGold is debt-free: the Nebari facility was repaid in 2025 (C$17.8 million). At 31 March 2026 it held C$84.5 million of cash and C$20.0 million of short-term investments against a C$6.9 million SRSR payment obligation (US$5.4 million to 11 January 2028) and C$1.4 million of leases; the reclamation provision is C$1.9 million. A C$12.6 million flow-through commitment runs to the end of 2026 (C$7.5 million remaining). Against C$271.0 million of Goldboro capital, Section 7 sizes the gap at C$178.7 million; Appian’s US$175 million debt letter of intent (25 September 2025) is non-binding. Cash rose from C$16.4 million at the end of FY2024 to C$87.7 million a year later on the Appian royalty sale and the shares issued in 2025; at the FY2025 burn of C$35.9 million, the March 2026 balance covers about three years of spending before any construction capital.

Hedge book. None — the company is unhedged on gold. Its currency exposure is small: a 10% move in the Canadian dollar changes the comprehensive loss by C$0.5 million.

Capital returns and share count. No dividend and no buyback. Common shares rose from a 65.4 million weighted average in FY2024 to 247.9 million at 31 March 2026 and 255.9 million pro forma in August 2026; 31.3 million warrants and 1.8 million options were in the money at 31 March 2026, worth C$37.3 million on exercise.

4. Management, strategy & structure

4.1 Management & governance

Kevin Bullock has been President and CEO since December 2024; he was the founding CEO of Goldcrest and Volta Resources, sold to B2Gold in 2013, and is a director of B2Gold. Orin Baranowsky has been CFO since April 2021, after CFO roles at Blue Thunder Mining and Stornoway Diamond. James Gowans is the non-executive Chair and also chairs the Technical, Health, Safety and Environment Committee, so the Chair and CEO roles are separate. Seven directors stand for election, four independent (57.1%); the committees are Audit; Compensation, Governance and Nominating; and Technical, Health, Safety and Environment. No related-party transactions were entered into in Q1 2026, and directors hold 3,755,903 shares.

4.2 Strategy

The plan is sequential: build Goldboro first, then Goliath. The 2026 outlook names an updated Goldboro resource and FS, an early-works program in H2 2026, up to 30,000 m of infill drilling at Goldboro and up to 25,000 m at Goldlund. Funding has come from royalty sales (Sprott in 2022, Appian in 2025) and equity, with project debt still at the letter-of-intent stage. The sequencing is a stated choice — the Q1 2026 MD&A records the decision to advance Goldboro towards construction before the Goliath Complex — so Goliath waits on Goldboro’s cash flow, and the model funds it from there rather than from a second raise.

4.3 Ownership & structure

The portfolio was assembled by acquisition — Signal Gold, which brought Goldboro (closed 2024), and Blackwolf Copper and Gold, which brought Niblack (2024–25). The one joint venture is Weebigee-Sandy Lake. No holder owns 10% or more; there are no offtakes or strategic investors. Obligations are the Sprott minimum payments and the flow-through commitment. The CRA has reassessed past flow-through renunciations, reclassifying about $1.8 million of exploration expense to operating expense and $2.2 million to development expense — a contingency, not a provision.

Table 5. Capital structure

Item Value As of
Common shares, pro forma basic / fully diluted 255.9 m / 363.8 m Aug 2026
Warrants 100.4 m at C$0.84–1.92, average C$1.67 Aug 2026
Royalties Appian 2.9% NSR (Goldboro); Sprott 2.2% NSR (Goliath) 31 Mar 2026
Debt nil; US$175 m Appian letter of intent, non-binding 31 Mar 2026

Source: NexGold corporate presentation, August 2026; Q1 2026 interim statements and MD&A.

5. ESG & sustainability

NexGold’s licence-to-operate record is its agreements and permits: the Benefits Agreement with the Assembly of Nova Scotia Mi’kmaw Chiefs (December 2024), whose Implementation Committee has met since January 2026, and the full Goldboro permit set. Goldboro’s design uses a fully lined tailings facility for 16.4 Mt of tailings. No ESG framework alignment, emissions target or safety frequency is disclosed (n/d), so the dimension is scored on agreements, not delivered performance. At Goliath the 2019 federal EA decision is the permitting record; its Indigenous agreements are not itemised in the filings read, so the score leans on Goldboro.

6. Risks

Table 6. Risk register

Risk Type Likelihood / impact (1–⁠5) Exposure Mitigant
Goldboro capex and funding gap Balance sheet / counterparty 4 / 4 C$271.0 m capital on 2021 costs; C$178.7 m gap C$104.5 m cash; Appian letter of intent
Gold price reversion Commodity 3 / 5 Unhedged, pre-revenue No debt to service
Equity dilution Dilution 3 / 4 Gap = 58.2% of market cap Royalty and debt alternatives
Goldboro build and ramp Operational 3 / 4 First build; ramp not guided All key permits in hand
Goliath permitting Jurisdiction / ESG 2 / 3 Federal EA 2019; later permits ahead Second build, no deadline
Goliath grade and economics Operational 2 / 3 1.3 g/t reserve; 2022 costs Optimization studies
Capital spread across assets Execution 2 / 2 Two provinces plus Alaska Goldboro sequenced first
Canadian dollar move Currency 3 / 3 USD/CAD −10% / +10% moves NAV/share to C$4.99 / C$6.51 (Section 7.5) Study costs and capital in C$; no hedge

Source: NexGold Q1 2026 and FY2025 MD&A risk sections; scores are the author’s assessment.

Section 7 prices the first four: the equity raise for the gap, the dated study costs, the grid and a one-year schedule slip. The top three share one cause — Goldboro’s capital is not yet raised. Gold reversion matters less to the read than it looks, since the deep-bear blend at US$3,000/oz and a 9% rate still sits above the price; a capital overrun works through the gap and the dilution at once, which is why the 25% cost case, at C$4.67 a share, is the harsher test.

Figure 5. Risk matrix — likelihood against impact

Impact (1–5)
5
4
3
2
1
Goldboro capex & funding 16
Gold price reversion 15
Equity dilution 12
Goldboro build & ramp 12
Goliath permitting 6
Goliath grade & economics 6
Capital & management spread 4
1
Rare
2
3
4
5
Likely
Likelihood (1–5)

Figure data: Table 6. Each point prints its likelihood × impact score; the shaded region is the high-likelihood, high-impact quadrant (likelihood ≥ 3.5 and impact ≥ 3.5). Ratings are the author’s assessment, not disclosed figures.

7. Valuation

Valuation as of 5 August 2026, in Canadian dollars. Horizon: spot fair value. Price deck: base gold US$4,000/oz, the representative of the trailing averages of the COMEX front-month close — US$4,303.36 (3-month), US$4,587.45 (6-month) and US$4,322.18 (12-month) to 31 July 2026 — snapped to the fixed US$3,000–5,000/oz grid and leaning low on the 2026 spike, with every grid price run as a scenario (deep bear US$3,000 to deep bull US$5,000). Discount rate 5% real; FX US$1 = C$1.4029 (Bank of Canada, 31 July 2026); share price C$1.20 (TSXV close, 31 July 2026). Development-stage risk sits in the row weights: Goldboro 0.60×, Goliath 0.40×.

NexGold is valued as a developer: Goldboro holds a 2022 feasibility study and every key permit but neither a construction decision nor its financing, and the Goliath Gold Complex holds a 2023 prefeasibility study. The method follows the How to Value Commodity Stocks guide. Each project is built from its own study lines — average production, all-in sustaining cost, initial and closure capital — at this deck and a statutory tax, risked for its stage, and the Goldboro funding gap is raised in equity before the per-share value is struck. Table 7 lists the inputs the result turns on; the full register is Table 21.

Table 7. Load-bearing inputs — the figures the valuation turns on (full source register: Table 21)

Input Value Where §7 uses it Source
Goldboro FS — after-tax NPV (5%) at US$1,600/oz C$328 m Table 10, block 1 — calibration Filed | Q1 2026 MD&A | “After-Tax NPV (5%)" | p.7
Goldboro FS — initial / reclamation and other capital C$271.0 m / C$50.3 m Table 10, block 1; Table 11 — funding gap Filed | Q1 2026 MD&A | “Initial Capital (C$M)" | p.7
Goldboro FS — AISC and FX basis US$849/oz at US$1 = C$1.25 Table 10, block 1 — unit cost Filed | Q1 2026 MD&A | “AISC (US$/oz Au)" | p.7
Goldboro FS — production and mine life 100 koz/yr over 10.9 years Table 10, block 1; Table 13 Filed | Q1 2026 MD&A | “Avg. Annual Prod. – Au (koz)" | p.7
Goldboro Probable reserve (eff. 15 Dec 2021) 1,150,200 oz Table 10, block 3; Table 16 Filed | Q1 2026 MD&A | “Probable Mineral Reserve” | p.8
Goldboro — Appian NSR (sold 29 Sep 2025) 2.9% NSR Table 10, block 1 — deck × (1 − 2.9%) Filed | Q1 2026 interim FS | “Appian Royalty” | p.12
Goliath PFS — post-tax NPV (5%) at US$1,750/oz C$336 m Table 10, block 2 — calibration Filed | Q1 2026 MD&A | “Post-tax NPV @ 5%" | p.12
Goliath PFS — initial capital and AISC C$335 m · US$1,072/oz Table 10, block 2 Filed | Q1 2026 MD&A | “Initial Capital Cost” | p.12
Goliath Complex P&P reserve (PFS) 1,267 koz Table 10, block 3; Table 16 Filed | Goliath Gold Complex PFS technical report | Table 1-6: Mineral Reserves Estimate | “Proven & Probable” | p.49
Goliath — Sprott NSR 2.2% NSR Table 10, block 2 — deck × (1 − 2.2%) Filed | Q1 2026 MD&A | Sale of Royalty to SRSR | “the Sprott Royalty” | p.19
Cash / short-term investments, 31 Mar 2026 C$84,482,339 / C$20,000,000 Table 11 — net cash Filed | Q1 2026 interim FS | Statement of financial position | “Cash and cash equivalents” | p.2
SRSR payment obligation, current / non-current C$3,294,244 / C$3,630,255 Table 11 — net cash Filed | Q1 2026 interim FS | Statement of financial position | “SRSR payment obligation” | p.2
Shares, diluted basis 262.5 m Table 11 — per share Derived | 255.9 m pro forma basic (August 2026 corporate presentation p.20) + 2.0 m option and warrant shares (treasury: 33.1 m in the money at 31 Mar 2026 with C$37.3 m proceeds, at C$1.20) + 4.6 m RSUs, DSUs and share units (Q1 2026 MD&A p.26)
Gold, 3-, 6-, 12-month averages US$4,303.36 · US$4,587.45 · US$4,322.18/oz Figure 7, Table 17 — deck Market | COMEX gold front-month (GC=F) daily closes, Yahoo Finance chart series captured 11 Oct 2026 (Market/yahoo_gcf_daily_20261011.json) | means of 63 / 125 / 251 sessions

Source: each row’s filing as cited — NexGold’s Q1 2026 and FY2025 filings and the study summaries on SEDAR+; deck rows per the COMEX gold front-month daily series and the Bank of Canada daily exchange rates.

Metal Pilot Premium

Valuation workings — Premium

The workings behind this valuation — the method, the models, the sensitivity grids and the scenarios, 11 tables and 3 figures in all — are for Metal Pilot Premium members.

  • 7.1 Method selection
  • 7.2 Net asset value
  • 7.3 Relative valuation
  • 7.4 Further weighted methods
  • 7.5 Cross-checks
  • 7.6 Scenarios & fair value

Want to see one first? The Newmont (NEM) valuation is open to every reader.

Create a Metal Pilot accountLog in

See Premium plansRead a free example

You are signed in, and your plan does not include valuation workings. They come with Metal Pilot Premium.

Upgrade to Premium

The premium section could not be loaded right now.

Premium — unlocked

8. Near-term catalysts (1–3 years)

The catalysts are Goldboro’s, in the order of the company’s outlook; Goliath’s follow its financing.

Table 19. Near-term catalysts (1–3 years)

Catalyst Timing Why it matters
Goldboro resource and FS update 2026 (company outlook) Resets the 2021 costs and the US$1,600/oz deck the financing will rest on
Goldboro early-works program H2 2026 First construction activity on a permitted site
Goldboro financing and construction decision 2026 (company expects; none made at 31 Mar 2026) Lifts Goldboro off its 0.60× stage weight and sets the dilution
Goldboro infill drilling, up to 30,000 m 2026 Firms the first mining years
Goldlund drilling, up to 25,000 m; Goliath optimization 2026 Rebuilds the second project’s plan
End of the Sprott minimum payments Earlier of 31 Dec 2027 or commercial production Removes US$500,000 a quarter of cash outflow

Source: NexGold Q1 2026 MD&A (Management Outlook for 2026; Sale of Royalty to SRSR) and the August 2026 corporate presentation (p.4, construction decision). Timing is the company’s, not guaranteed.

8.1 Takeover optionality

Target case. Goldboro is a permitted, feasibility-stage open pit in Canada with a signed Mi’kmaw benefits agreement, owned by a debt-free company with no 10% holder — the profile of an asset a producer buys to replace reserves.

Disqualifiers. Two royalties already take 2.9% and 2.2% of the projects’ revenue, a buyer of one project inherits the other, and Goldboro’s capital estimate is about to be reset.

Acquirers. No filing in the source set links a buyer to NexGold. The CEO’s seat on the B2Gold board is a disclosed connection, not evidence of intent, so no acquirer is named.

Effect on the verdict. None: no transaction method carries weight in Section 7 (FCF-yield support takes its place), so takeover optionality sits outside the fair value.

9. Rating & verdict

NexGold is scored on the nine-dimension scorecard against the Section 2.7 peers (Artemis Gold, Skeena Resources, Osisko Development) on the developer weighting: balance sheet, management, asset quality and reserves carry 15% each, the other five 8% each; cost is scored on the study estimates and labelled so.

Figure 9. Scorecard by dimension, 5 August 2026

Balance sheet★★15%
Management★★★15%
Assets & scale★★★15%
Reserves & life★★★15%
Growth★★★★8%
Jurisdiction★★★★8%
Cost & margins★★★8%
Capital allocation★★★8%
ESG★★★8%
Score by dimension Weighted composite ★★★ (3.01)
Each ring is one star; the outer ring is ★★★★★. Weights in Table 20.

Figure data: Table 20. Each spoke prints its stars and weight; the dashed ring is the weighted composite, 3.01/5.

Table 20. The NexGold scorecard

Dimension Weight Score Weighted Rationale
Balance sheet & liquidity 15% ★★ 0.30 Debt-free with C$104.5 m cash and investments (31 Mar 2026), but a C$178.7 m Goldboro gap — 58.2% of market cap — behind a non-binding letter of intent; below Skeena, in development since December 2024
Management & governance 15% ★★★ 0.45 CEO Bullock sold Volta to B2Gold (2013); four of seven directors independent (57.1%), non-executive Chair James Gowans; no mine built by this team — the peer median
Asset quality & scale 15% ★★★ 0.45 190 koz/yr from two assets, level with Cariboo (191.8) and below Eskay Creek (228) and Blackwater (438); Goldboro at 2.26 g/t
Reserves, life & replacement 15% ★★★ 0.45 2.42 Moz P&P (Goldboro Probable, eff. 15 Dec 2021; Goliath PFS, 22 Feb 2023) over 10.9 and ~13 years — between the peers Cariboo (2.07 Moz) and Eskay Creek (3.34 Moz)
Growth & optionality 8% ★★★★ 0.32 A second studied project behind the first, where every peer is single-asset; 1,159,000 oz of Goldboro underground M&I beyond the pit plan
Jurisdiction & geopolitics 8% ★★★★ 0.32 Nova Scotia and Ontario; every key Goldboro permit in hand, Goliath federal EA 2019 — level with the British Columbia peers
Cost position & margins (FS estimate) 8% ★★★ 0.24 Study AISC US$849/oz and US$1,072/oz against peer studies of US$781 (Blackwater) to US$1,157 (Cariboo) — mid-field, on the oldest costs
Capital allocation & returns 8% ★★★ 0.24 No dividend — none is expected before first gold, the norm across the developer peer set; Nebari debt repaid and its NSR bought back, financed by the Appian NSR and equity; weighted shares 65.4 m to 168.6 m in FY2025
ESG & licence to operate 8% ★★★ 0.24 Mi’kmaw Benefits Agreement and a lined tailings facility; no framework or safety rate disclosed — the developer-peer median
Composite 100% ★★★ 3.01 Average

Weighted average = 0.30 + 0.45 + 0.45 + 0.45 + 0.32 + 0.32 + 0.24 + 0.24 + 0.24 = 3.01/5 → rounds to ★★★, Average.

Source: this analysis; evidence in Sections 2–6 from the NexGold Q1 2026 and FY2025 filings and the peers’ AIFs (Table 3).

The two-axis verdict. As of 5 August 2026, quality Average (★★★) × value Undervalued → a re-rating candidate; the catalyst is a financed Goldboro construction decision. The blended base-case fair value of C$7.17 at US$4,000/oz implies +497.7% against the C$1.20 close; the deep-bear blend of C$4.20 sits above the price, so no wide-band qualifier attaches, and the read holds down to ~US$1,305/oz. The market is pricing roughly US$1,132/oz gold, held flat over both mine lives — below Goldboro’s own US$1,600/oz study deck. The targets sit at the developer anchors moved by the scorecard: balance sheet (★★, −0.03) and jurisdiction (★★★★, +0.01) take the driver line to −0.02 — P/NAV 0.98×, FCF yield 7.14%, EV/reserve US$294/oz. Bull: even a fully diluted, risked NAV is several times the price. Bear: the study costs are four years old and the gap is not financed. A Goldboro package on terms close to the modelled raise closes the discount; a stalled debt facility and a deeper raise widen it. This is an analytical read, not a recommendation.

To rank NexGold against every listed gold developer on these dimensions, screen the Metal Pilot gold dataset.

10. Sources, methodology & disclaimer

10.1 Sources, methodology & data vintage

Company filings (SEDAR+): Q1 2026 interim financial statements and MD&A (14 May 2026); FY2025, FY2024 and FY2023 audited statements and MD&A; the Goldboro FS technical report (January 2022; reserve effective 15 December 2021); the Goliath Gold Complex PFS technical report (February 2023); the May 2026 management information circular; the August 2026 corporate presentation. Peers: Artemis Gold FY2024 AIF, Skeena FY2025 AIF and Q1 2026 MD&A, Osisko Development FY2025 AIF. Market: COMEX gold front-month daily closes to 31 July 2026; Bank of Canada USD/CAD 1.4029 (31 July 2026); the TSXV close of 31 July 2026.

Methodology. Archetype developer, sector precious-metal miner. Analysis as of 5 August 2026, market data at the 31 July 2026 close. Base deck gold US$4,000/oz on the fixed US$3,000–5,000/oz grid, from 3-, 6- and 12-month averages of US$4,303.36, US$4,587.45 and US$4,322.18; every grid price run as a scenario. Scorecard on the developer weights (four dimensions at 15%, five at 8%) against the three peers on quality metrics; valuation weights risked P/NAV 55%, FCF-yield support 25%, EV/reserve 20%. Refreshed on each annual report and on material events (a construction decision, a financing close).

Re-run log. 5 August 2026, original analysis — 3.8/5 Solid, Undervalued (wide band). 11 October 2026, pipeline rework — the facts file and the model rebuilt on filed rows; the Appian and Sprott NSRs moved into the rows; Niblack no longer valued; the scorecard re-scored (3.8 → 3.0: balance sheet ★★★★ → ★★, reserves, management and ESG ★★★★ → ★★★, jurisdiction ★★★★★ → ★★★★) and its stars handed to the driver line (Σ 0.00 → −0.02): blend C$7.20 (implied +499.6%), NAV/share C$5.73, market-implied deck US$1,126/oz, Undervalued. 11 October 2026, gate fixes — the Goliath P&P taken from the PFS technical report (1,267 koz, not the MD&A’s rounded 1.3 Moz; group P&P 2.42 Moz) and the FCF-yield target carried unrounded at 7.14%: NAV/share C$5.75, blend C$7.17 (implied +497.7%), range C$4.20–9.26, market-implied deck US$1,132/oz; the read stays Undervalued.

Omitted figures and data gaps. No asset map is built, and there is no financial-line or safety-trend chart (no production or safety series). Not on record: the capex lines, an archived consensus target and NexGold’s own P/NAV history. The model’s full cross-check and sensitivity tables are in claude/valuation-models/nexgold-mining-nexg.out.md.

Table 21. Full source register for the valuation (load-bearing subset: Table 7)

InputValueAs ofWhere §7 uses itSource
Condensed consolidated interim financial statements, 31 March 2026
Goldboro Project — interest, operator, country100% owned; operator NexGold; Guysborough County, Nova Scotia, Canada31 Mar 2026§2 asset map; V28 vehicle mapFiled | Q1 2026 interim FS | Note 10 | "The Goldboro Project is a 100% owned" | p.11
Goldboro — Appian 2.9% NSR (sold 29 Sep 2025)2.9% NSR on the Goldboro property sold to Appian Capital Advisory for C$33,410,400 (US$24.0 m)31 Mar 2026V34 encumbrance — the Goldboro NAV row nets itFiled | Q1 2026 interim FS | "Appian Royalty" | p.12
Net loss, Q1 2026 / Q1 2025C$(11,374,724) / C$(9,420,530)31 Mar 2026§3 latest periodFiled | Q1 2026 interim FS | "Net income (loss) for the period" | p.5
Exploration and evaluation expense, Q1 2026 / Q1 2025C$8,835,372 / C$6,594,24931 Mar 2026§3; V20 corporate burnFiled | Q1 2026 interim FS | "Exploration and evaluation" | p.3
Cash and cash equivalentsC$84,482,33931 Mar 2026V20 bridge — cashFiled | Q1 2026 interim FS | Statement of financial position | "Cash and cash equivalents" | p.2
Short term cash investments (180-day GIC)C$20,000,00031 Mar 2026V20 bridge — cashFiled | Q1 2026 interim FS | Statement of financial position | "Short term cash investments" | p.2
Restricted cash (non-current)C$803,23631 Mar 2026V20 bridge — excluded from cashFiled | Q1 2026 interim FS | Statement of financial position | "Restricted cash" | p.2
Accounts receivable and prepaid expensesC$2,431,23531 Mar 2026V20 working capitalFiled | Q1 2026 interim FS | Statement of financial position | "Accounts receivable and prepaid expenses" | p.2
Investments (equities)C$1,468,53731 Mar 2026V20 bridge — investmentsFiled | Q1 2026 interim FS | Statement of financial position | "Investments" | p.2
Accounts payable and accrued liabilitiesC$6,279,55331 Mar 2026V20 working capitalFiled | Q1 2026 interim FS | Statement of financial position | "Accounts payable and accrued liabilities" | p.2
Long-term payables (lease payable): current / non-currentC$273,230 / C$1,141,59631 Mar 2026V20 bridge — lease liabilitiesFiled | Q1 2026 interim FS | Statement of financial position | "Long-term payables" | p.2
SRSR payment obligation: current / non-currentC$3,294,244 / C$3,630,25531 Mar 2026V20 bridge — debt-like (Sprott Minimum Payments)Filed | Q1 2026 interim FS | Statement of financial position | "SRSR payment obligation" | p.2
Nebari Facility (US$12.0 m, 11.4%) — carrying valueC$0.0; repaid in full in 2025 (repayment C$(17,824,981))31 Mar 2026V20 bridge — debtFiled | Q1 2026 interim FS | Note 12 | "Repayment" | p.13
Provision for reclamation (non-current; no current portion)C$1,869,31131 Mar 2026V45 rehabilitation provisionFiled | Q1 2026 interim FS | Statement of financial position | "Provision for reclamation" | p.2
Management's discussion and analysis, three months ended 31 March 2026
Goldboro — stage and permitsFeasibility study (Jan 2022); all key permits for construction and operations obtained (Fisheries Act Authorization 31 Oct 2025)31 Mar 2026V35 stage risk; §2 approvalsFiled | Q1 2026 MD&A | Goldboro | "obtained all key permits for the Goldboro Project" | p.10
Goldboro — scheduleEarly works construction program planned for H2 2026; no construction decision made; updated MRE and FS in 202631 Mar 2026V41 schedule; schedule-slip sensitivityFiled | Q1 2026 MD&A | Project Development | "No construction decision has been made" | p.8
Goldboro FS — price and FX basisUS$1,600/oz gold; US$1 = C$1.2511 Jan 2022V27 NPV interpolationFiled | Q1 2026 MD&A | "exchange rate assumption of 1US$:1.25C$" | p.8
Goldboro FS — after-tax NPV (5%), IRR, paybackC$328 m; IRR 25.5%; payback 2.9 years11 Jan 2022V27 per-asset NAV rowFiled | Q1 2026 MD&A | "After-Tax NPV (5%)" | p.7
Goldboro FS — initial, sustaining, reclamation capitalInitial C$271.0 m; sustaining C$63.1 m; reclamation and other C$50.3 m11 Jan 2022V27 model row; remaining capitalFiled | Q1 2026 MD&A | "Initial Capital (C$M)" | p.7
Goldboro FS — unit costsCash costs US$773/oz; AISC US$849/oz; total operating costs C$67.05/t milled11 Jan 2022V27 model row; §2 cost curveFiled | Q1 2026 MD&A | "AISC (US$/oz Au)" | p.7
Goldboro FS — production and life100 koz/yr Au; mine life 10.9 years; mill feed 2.26 g/t; recovery 95.8%; strip 8.0:111 Jan 2022V27 volume row; life basisFiled | Q1 2026 MD&A | "Avg. Annual Prod. – Au (koz)" | p.7
Goldboro — Probable Mineral Reserve (NI 43-101, eff. 15 Dec 2021)15,798,900 t at 2.26 g/t for 1,150,200 oz (East Pit 446,000 oz; West Pit 704,200 oz)15 Dec 2021V40 reserve tier; EV/ozFiled | Q1 2026 MD&A | "Probable Mineral Reserve" | p.8
Goldboro — M&I resource, OP + UG (inclusive of reserves; eff. 15 Nov 2021)21,594,000 t at 3.72 g/t for 2,581,000 oz (OP 1,422,000 oz; UG 1,159,000 oz)15 Nov 2021V40 resource tier; V41 conversion rowFiled | Q1 2026 MD&A | Goldboro Mineral Resource Estimate | "Measured + Indicated" | p.7
Goliath — stage and approvalsPFS (Feb 2023); federal EA decision statement 2019; second build after Goldboro; optimization studies under way31 Mar 2026V35 stage risk; §2 approvalsFiled | Q1 2026 MD&A | Management Outlook for 2026 | "Environmental Assessment approvals in place" | p.5
Goliath PFS — price and FX basisUS$1,750/oz gold; US$21/oz silver; USD:CAD 0.75 (US$1.00 = C$1.3333)22 Feb 2023V27 NPV interpolationFiled | Q1 2026 MD&A | "Exchange Rate" | p.12
Goliath PFS — NPV (5%), IRR, paybackPost-tax C$336 m, IRR 25.4%, payback 2.8 years; pre-tax C$469 m, IRR 29.3%22 Feb 2023V27 per-asset NAV rowFiled | Q1 2026 MD&A | "Post-tax NPV @ 5%" | p.12
Goliath PFS — capitalInitial C$335 m; sustaining C$198 m; closure C$29 m; salvage C$10 m22 Feb 2023V27 model row; remaining capitalFiled | Q1 2026 MD&A | "Initial Capital Cost" | p.12
Goliath PFS — unit costs (by-product)LOM cash costs US$935/oz, AISC US$1,072/oz; first five years cash costs US$820/oz, AISC US$1,008/oz22 Feb 2023V27 model row; §2 cost curveFiled | Q1 2026 MD&A | "All-in Sustaining Cost" | p.12
Goliath PFS — production90 koz/yr Au average; 1,175 koz Au LOM; peak 128 koz (year 2); head grade 1.30 g/t; recovery 92.8%22 Feb 2023V27 volume row; life basisFiled | Q1 2026 MD&A | "Total Average Annual Production" | p.12
Goliath Complex — resources by depositGoliath M&I OP 798,900 oz + UG 325,100 oz, Inferred 91,500 oz; Goldlund Indicated 940,000 oz, Inferred 703,000 oz; Miller Indicated 74,600 oz, Inferred 4,500 oz22 Feb 2023V40 resource tier; V41 conversion rowFiled | Q1 2026 MD&A | Goliath Gold Complex | "Measured and Indicated mineral resource categories" | p.10
Goliath — Sprott (SRSR) 2.2% NSR2.2% NSR on all Goliath Complex claims, sold 11 Apr 2022 for C$25,178,000 (US$20.0 m); halves after 1.5 Moz produced; US$500,000 quarterly Minimum Payments until the earlier of 31 Dec 2027 and commercial production31 Mar 2026V34 encumbrance; V20 bridge (payment obligation)Filed | Q1 2026 MD&A | Sale of Royalty to SRSR | "the Sprott Royalty" | p.19
Sprott minimum payment obligationUS$5.4 m; maturity 11 Jan 202831 Mar 2026V20 maturitiesFiled | Q1 2026 MD&A | Contractual obligations | "Sprott minimum payment obligation" | p.28
Outstanding securities at 31 Mar 2026Common 247,884,140; options 3,077,298; RSUs 3,147,130; DSUs 883,326; warrants 102,310,748; share units 585,689; total 357,888,33131 Mar 2026V20 per-share basisFiled | Q1 2026 MD&A | Share Capital | "Outstanding Share and Equity-instrument Information" | p.26
In-the-money options and warrants, 31 Mar 20261,763,173 options and 31,344,378 warrants ITM; C$37,295,225 on exercise31 Mar 2026V20 treasury-method dilutionFiled | Q1 2026 MD&A | Share Capital | "in-the-money" | p.26
Derived
Goldboro — M&I exclusive of reserves (approximate)1,430,800 oz15 Dec 2021V40 resource tierDerived | a-gb-resource-mi (2,581,000 oz) − a-gb-reserve (1,150,200 oz)
Goliath Complex — M&I and Inferred totalsM&I 2,138,600 oz; Inferred 799,000 oz22 Feb 2023V40 resource tierDerived | a-ggc-resource (798,900 + 325,100 + 940,000 + 74,600; 91,500 + 703,000 + 4,500)
Shares, diluted (treasury method at C$1.20)262.5 m31 Jul 2026Table 11 — per shareDerived | 255.9 m pro forma basic (August 2026 corporate presentation p.20) + 2.0 m option and warrant shares (treasury: 33.1 m in the money at 31 Mar 2026 with C$37.3 m proceeds, at C$1.20) + 4.6 m RSUs, DSUs and share units (Q1 2026 MD&A p.26)
Management's discussion and analysis, year ended 31 December 2025
Goldboro — Nebari 0.6% NSR (sold 13 Dec 2024) — bought backBought back on 29 Sep 2025 under the Goldboro Buy-Down Option for US$6,900,000 (C$9,605,490); extinguished31 Dec 2025V34 encumbrance (none — extinguished)Filed | FY2025 MD&A | Sale of Royalty to Nebari Royalty I ULC | "bought back the Nebari Royalty" | p.23
Appian project-financing LOI (Goldboro)Non-binding LOI, 25 Sep 2025: senior secured credit facility of up to US$175 m for Goldboro development and construction31 Dec 2025V20 funding; V41 scheduleFiled | FY2025 MD&A | 2025 Highlights | "senior secured credit facility of up to US$175 million" | p.5
Management's discussion and analysis, year ended 31 December 2024
Goliath Gold Complex — interest, operator, country100% held; operator NexGold; Kenora Mining Division, Ontario, Canada (Goliath, Goldlund, Miller deposits)31 Dec 2024§2 asset map; V28 vehicle mapFiled | FY2024 MD&A | Goliath Complex | "Goliath Project is held 100% by the Company" | p.17
NI 43-101 prefeasibility study technical report, Goliath Gold Complex, 22 Feb 2023
Goliath Complex — Proven and Probable Mineral Reserve (PFS)1,267 koz Au in 30,319 kt at 1.30 g/t (Proven 4,565 kt at 1.43 g/t for 210 koz; Probable 25,754 kt at 1.28 g/t for 1,057 koz)22 Feb 2023V40 reserve tier; EV/ozFiled | Goliath Gold Complex PFS technical report | Table 1-6: Mineral Reserves Estimate | "Proven & Probable" | p.49
Consolidated financial statements, year ended 31 December 2025
Non-capital losses carried forward, 2025 / 2024C$66,260,743 / C$58,616,34431 Dec 2025V43 tax basisFiled | FY2025 audited FS | "Non-capital losses carried forward" | p.44
n/d
Hedge booknone disclosed31 Mar 2026V42 hedge bookn/d · checked: Q1 2026 interim FS (no 'hedg' hit), Q1 2026 MD&A, FY2025 audited FS — no derivative hedge programme
Corporate presentation, August 2026
Market capitalisation (company figure)C$307.1 m1 Aug 2026§1 statcard; V20 EVFiled | August 2026 corporate presentation | Capital Markets Data | "Market Capitalization" | p.20
Shares outstanding (pro forma, after recent financings) / fully diluted255.9 m / 363.8 m1 Aug 2026V20 per-share basisFiled | August 2026 corporate presentation | Capital Markets Data | "Fully Diluted" | p.20
Market data — Bank of Canada FX and COMEX gold (GC=F) series to 31 Jul 2026, captured 11 Oct 2026
FX USD/CAD on the market dateUS$1.00 = C$1.402931 Jul 2026Tables 10, 16 — deck and reserves to C$Market | Bank of Canada daily exchange rate USD/CAD, 31 Jul 2026 (Market/boc_fxusdcad_20261007.csv)
Gold trailing averages to 31 Jul 2026 (US$/oz): 3 / 6 / 12-monthUS$4,303.36 · US$4,587.45 · US$4,322.1831 Jul 2026Figure 7, Table 17 — deckMarket | COMEX gold front-month (GC=F) daily closes, Yahoo Finance chart series captured 11 Oct 2026 (Market/yahoo_gcf_daily_20261011.json) | means of 63 / 125 / 251 sessions
Gold five-year average, Aug 2021 – Jul 2026 (US$/oz)US$2,609.7231 Jul 2026Table 18, field 2 — anchors heldMarket | COMEX gold front-month (GC=F) daily closes, Yahoo Finance chart series captured 11 Oct 2026 (Market/yahoo_gcf_daily_20261011.json) | mean of 1,258 sessions
Gold 12-month high / low close (US$/oz)US$5,318.40 / US$3,358.7031 Jul 2026§7.6 — market-implied deckMarket | COMEX gold front-month (GC=F) daily closes, Yahoo Finance chart series captured 11 Oct 2026 (Market/yahoo_gcf_daily_20261011.json) | 1 Aug 2025 – 31 Jul 2026

Source: each row’s document, page and quoted label as cited — NexGold’s filings on SEDAR+; market rows per the dated series named in the row.

10.2 Disclaimer & disclosure

This analysis is for informational purposes only and is not investment advice; do your own research or consult a licensed advisor. It is a point-in-time snapshot as of 5 August 2026 — the share price, the share count and the gold price move, and every figure is an estimate as of that date. NexGold is a pre-production developer whose value rests on studies and on financing not yet committed. The two-axis verdict is an analytical read, not a buy or sell instruction. This report was prepared with AI assistance; figures were sourced from NexGold’s filings and reviewed, but readers should verify before acting. As of 18 November 2026, the author holds no position in the company this analysis covers.