Canada Nickel (CNC) — Stock Analysis 2026 [3.3]

Nickel Battery Metals Company Analysis
CAD

Analysis as of 22 October 2026. Price deck: base nickel US$17,000/t — the representative trailing average on the fixed US$13,000–21,000/t grid — with every grid price run as a scenario (deep bear US$13,000, bear US$15,000, base US$17,000, bull US$19,000, deep bull US$21,000) and the analyst consensus as a 0% cross-check — no spot price. Iron ore, the largest by-product, runs on its own US$100/t deck. At C$0.98 the shares price in a market-implied nickel deck of ~US$15,672/t. Market data is the 22 October 2026 TSXV close; figures are Canadian dollars unless marked US$. Refreshed on each permitting, financing or construction milestone. Rating: ★★★½ Solid / Modestly undervalued (wide band).

This Canada Nickel (CNC) stock analysis covers a company with one project to build: Crawford, near Timmins in Ontario, with 3,789 kt of nickel in proven and probable reserves and a 41-year mine plan in its 2023 feasibility study. The thesis in one line: the deposit is large, long-lived and low-cost on the study’s numbers, but the company has to raise about US$2.5 billion while it runs a working-capital deficit, so the funding terms decide how much of Crawford reaches today’s shareholder. Why now: the federal Decision Statement arrived on 31 July 2026, the construction permits are due in the third quarter of 2027, and a US$32 million bridge loan falls due on 9 November 2026. To compare Canada Nickel with every listed nickel company on reserves, grade and stage, use Metal Pilot’s nickel mining stock screener.

1. Snapshot & thesis

Canada Nickel Co. Inc. (TSXV: CNC; OTCQX: CNIKF), listed on the TSX Venture Exchange since February 2020, is a pre-production nickel company. By archetype it is a developer in the battery-metals sector (nickel): one feasibility-stage project, no production and no revenue. Crawford is wholly owned; around it the company holds the Timmins Nickel District, with published resources on nine properties, including Mann at 80%.

Figure 1. Canada Nickel in numbers

C$0.98 /sh
Share price — TSXV, 22 Oct 2026 · US$0.70
C$253.6 m
Market capitalisation — basic shares
3,789 kt Ni
Crawford proven + probable — 0.22% Ni
38 kt/yr
Recovered nickel — life-of-mine average
US$1.54/lb
Net AISC — feasibility study estimate
C$2,556 m
Initial capital — 2023 feasibility study
C$2,581 m
Funding gap — 1,018% of market cap
C$1.17 /sh
NAV per share — after financing, P/NAV 0.83×
C$1.17 /sh
Fair value — blend, range C$0.43–1.66
3.3/5
Quality rating — Solid
Modestly
undervalued
Valuation read — wide band, implied +19.2%
~US$15,672/t
Market-implied nickel deck

Source: Canada Nickel’s Q3 2026 condensed interim financial statements and MD&A and the Crawford feasibility technical report on SEDAR+; share price per Yahoo Finance at the 22 October 2026 TSXV close. NAV, fair value, funding gap and the market-implied deck per Section 7.

Table 1. Canada Nickel in numbers

Metric Value As of
Share price / market capitalisation C$0.98 (US$0.70) / C$253.6 m on 258.8 m basic shares 22 Oct 2026
Shares, basic / diluted (model) 258.8 m / 298.0 m 16 Sep 2026
Revenue nil (pre-production) FY2025
Crawford proven + probable reserve (100%) 1,715 Mt at 0.22% Ni; 3,789 kt Ni eff. 31 Aug 2023
Recovered nickel / net AISC 38 kt/yr life-of-mine / US$1.54/lb, feasibility study 1 Oct 2023
Cash margin at the net AISC, US$17,000/t 80.0% 22 Oct 2026
Initial capital / funding plan C$2,556 m / US$2.5 bn (US$1 bn equity, US$1.5 bn debt) Oct 2026
Cash / bridge loans C$8.1 m / C$48.1 m; working-capital deficit C$47.4 m 31 Jul 2026
Funding gap C$2,581.0 m, 1,018% of market capitalisation 22 Oct 2026
NAV per share / P/NAV C$1.17 / 0.83× 22 Oct 2026
Fair value (range) C$1.17 (C$0.43–1.66) 22 Oct 2026
Market-implied nickel deck ~US$15,672/t 22 Oct 2026
Quality rating / valuation read 3.3/5 Solid / Modestly undervalued (wide band), implied +19.2% 22 Oct 2026

Source: Canada Nickel’s Q3 2026 filings, the October 2026 investor presentation and the Crawford technical report on SEDAR+; share price per Yahoo Finance at the 22 October 2026 close. Margin = (US$7.71/lb − US$1.54/lb) ÷ US$7.71/lb, the base deck in pounds; the net AISC carries the study’s by-product credits. NAV, fair value, funding gap and the market-implied deck per Section 7.

Thesis in brief. Bull: Crawford’s reserve is more than four times the largest in the peer set, and its iron and chromium concentrates pull the study’s net AISC down to US$1.54/lb, which keeps Crawford’s NPV positive even at US$13,000/t. Bear: the company owes more in the short term than it holds in cash, the build needs about ten times today’s market value, and 36.9% of the mine’s payable value is iron, chromium and other by-products whose prices the market does not quote alongside nickel. What tips it: the price and mix of the US$2.5 billion package.

How to read this analysis: the statcards and Section 9 give the verdict; Sections 2–6 give the evidence and Section 7 the valuation.

2. Assets & operations

Crawford is a large, low-grade nickel sulphide deposit; the Nickel — A Complete Market Guide explains the market it sells into.

2.1 Portfolio overview

Table 2. Canada Nickel asset portfolio, by value

Asset Country Stage Interest Output Nickel reserve / resource Life Unit cost Listing / operator
Crawford Canada (Ontario) Feasibility study 2023; federal approval 31 Jul 2026 100% 38 kt/yr Ni recovered (life-of-mine) P&P 3,789 kt Ni at 0.22% 41 years Net AISC US$1.54/lb (study) TSXV:CNC (operator)
Deloro Canada (Ontario) Resource 100% — Indicated 300 kt Ni at 0.25% n/d n/d TSXV:CNC (operator)
Bannockburn Canada (Ontario) Resource n/d — Indicated 179.7 kt Ni at 0.28% n/d n/d TSXV:CNC (operator)
Nesbitt Canada (Ontario) Resource 100% — Indicated 57.5 kt Ni at 0.23% n/d n/d TSXV:CNC (operator)
Midlothian Canada (Ontario) Resource n/d — Inferred 1,683.8 kt Ni at 0.28% n/d n/d TSXV:CNC (operator)
Mann, Reid, Texmont and others Canada (Ontario) Resource Mann 80%; others n/d — in the district total, 10.3 Mt Ni M&I n/d n/d TSXV:CNC (operator)

Source: Canada Nickel’s Q3 2026 MD&A (interests, district resources, Nesbitt, Deloro), FY2025 MD&A (Mann), the Crawford, Bannockburn and Midlothian technical reports on SEDAR+. Only Crawford carries value in Section 7; the district resources have no study.

Crawford is the whole valuation: no other property has an economic study, so the eight district resources add exploration upside but no modelled value. The district’s nine published estimates total 10.3 Mt of nickel measured and indicated at 0.24% and 13.2 Mt inferred.

2.2 Value and resources by asset

Canada Nickel has no revenue, so the two figures split the enterprise NAV and the nickel resource instead.

Figure 2. Enterprise NAV by component, base case (C$ m)

Crawford (risked 0.50×)
Crawford M&I beyond the plan
768.9 · 87.1%
114.0 · 12.9%
Enterprise NAV components (C$ m), US$17,000/t and 10% real; no revenue to split

Figure data: Section 7, Tables 11 and 13.

Figure 3. Nickel measured and indicated resources by deposit (kt Ni, 100%)

Crawford (East + Main-West)
Mann, Reid, Texmont and others
Deloro
Bannockburn
Nesbitt
6,035.3 · 58.6%
3,727.5 · 36.2%
300.0 · 2.9%
179.7 · 1.7%
57.5 · 0.6%
Measured + indicated nickel (kt), inclusive of reserves; "others" = the 10.3 Mt district total less the named deposits

Figure data: Crawford technical report Tables 1-7 and 1-8 (effective 31 Aug 2023); Q3 2026 MD&A (district total, Nesbitt, Deloro); Bannockburn technical report.

2.3 Crawford

Ownership and encumbrances. Canada Nickel acquired 100% of the Crawford Nickel Sulphide Project in 2020 and operates it. The patented lands carry a 2% net smelter return royalty, after Noble bought its 5% royalty in December 2019; a third party holds a 5% net profits interest, payable from commercial production, of which up to 2.5% can be bought back for C$2 million. Neither holder is named in the filings. The study assumes the buy-down and an impact benefit agreement not yet negotiated; together they cost US$1,990 million over the mine’s life. Samsung SDI holds an option to buy a 10% direct interest for US$100 million with a life-of-mine nickel offtake.

Stage and approvals. In hand: the federal Decision Statement under the Impact Assessment Act (31 July 2026). Outstanding: the provincial and federal construction permits (Q3 2027) and the provincial operating permits (Q2 2029). The company plans a 27-month build from Q4 2027 to first production in Q4 2029, two years later than the study’s 2028 first full year.

The mine plan. Phase 1 runs 42 months at 60 kt/d of ore; Phases 2 and 3 run 26½ and 11¼ years at 120 kt/d. Head grade falls from 0.26% in Phase 1 to 0.17% in Phase 3, and nickel recovery from 48% to 25%, so output peaks at 48 kt/yr in Phase 2 before easing to 18 kt/yr. Two products are sold at the mine gate: a nickel concentrate carrying cobalt and the platinum-group metals, and an iron concentrate carrying iron, chromium and some nickel.

Table 3. Crawford study parameters (100% basis)

Parameter 2023 feasibility study (of record) 2025 FEED update (MD&A)
Post-tax NPV at 8% / IRR US$2,475 m / 17.1% US$2,810 m / 17.6%
Initial capital C$2,556 m (US$1,943 m) US$2,047 m
Total capital C$6,611 m (US$5,024 m): expansion C$2,105 m, sustaining C$1,950 m US$5,724 m
Closure C$175 m n/d
Payable metal, life of mine 3,130 Mlb Ni; 4,961 Mlb NiEq n/d
Net C1 / net AISC US$0.39/lb / US$1.54/lb operating cost US$10.60/t
Long-term nickel price US$21,000/t, 91% payable n/d
Study exchange rate C$1.00 = US$0.76 n/d

Source: Crawford technical report (effective 1 Oct 2023) Tables 1-12 and 1-14 and Section 22 on SEDAR+; FY2025 MD&A, updated engineering and project metrics. The FEED update has no technical report; Section 7 carries it at 0%.

Remaining capital and risk. All C$2,556 million of initial capital is still to spend. The one asset risk is the by-product dependence: credits of US$5.57/lb of nickel turn site costs into the US$1.54/lb net AISC, and iron alone is worth 19.9% of payable value at the study’s prices.

2.4 Other Timmins Nickel District properties

The district holds published resources but no studies. Deloro has 119 Mt indicated at 0.25% Ni and 498 Mt inferred; Nesbitt 24.5 Mt indicated at 0.23% and 152.1 Mt inferred; Bannockburn 63.2 Mt indicated at 0.28%; Midlothian 595.3 Mt inferred at 0.28%. Mann is held 80% through East Timmins Nickel. The regional properties carry vendor royalties of 1–2%, half of which the company can buy back.

2.5 Production, reserves & costs

Crawford’s reserve is 994 Mt proven at 0.24% Ni and 721 Mt probable at 0.20% under NI 43-101, effective 31 August 2023, with 215 kt of cobalt contained. The measured and indicated resource, inclusive of the reserve, adds 2,246 kt of nickel beyond the mine plan, and 3,726 kt sits in the inferred category.

Table 4. Reserves and resources by deposit

Deposit Category (code, effective date) Tonnes Grade Contained Ni
Crawford Proven (NI 43-101, 31 Aug 2023) 994 Mt 0.24% Ni 2,345 kt
Crawford Probable (NI 43-101, 31 Aug 2023) 721 Mt 0.20% Ni 1,444 kt
Crawford East M&I, inclusive / inferred 1,034.6 Mt / 157.3 Mt 0.23% / 0.23% 2,363.0 kt / 367.1 kt
Crawford Main-West M&I, inclusive / inferred 1,527.2 Mt / 1,535.8 Mt 0.24% / 0.22% 3,672.3 kt / 3,359.2 kt
Deloro Indicated / inferred (23 Jul 2026) 119 Mt / 498 Mt 0.25% / 0.25% 300 kt / 1.25 Mt
Nesbitt Indicated / inferred (23 Jul 2026) 24.5 Mt / 152.1 Mt 0.23% / 0.23% 57.5 kt / 351 kt
Bannockburn Indicated / inferred 63.2 Mt / 129.0 Mt 0.28% / 0.27% 179.7 kt / 342.9 kt
Midlothian Inferred (15 Dec 2025) 595.3 Mt 0.28% 1,683.8 kt

Source: Crawford technical report Tables 1-7 to 1-9; Bannockburn and Midlothian technical reports on SEDAR+; Q3 2026 MD&A (Deloro, Nesbitt).

Figure 4. Crawford nickel by category (kt Ni, 100%)

Contained Ni (kt)
4,000
3,000
2,000
1,000
0
2,345
1,444
2,246
3,726
Proven
Probable
M&I beyond reserve
Inferred
Category, NI 43-101, effective 31 Aug 2023; M&I beyond reserve = 6,035.3 inclusive less 3,789

Figure data: Crawford technical report Tables 1-7 to 1-9 on SEDAR+.

2.6 Peer positioning

The peer set for every star in Section 9 is four nickel developers, none in a pending deal: Centaurus Metals (ASX: CTM), EV Nickel (TSXV: EVNI), Lifezone Metals (NYSE: LZM) and Talon Metals (TSX: TLO). Each is compared on quality metrics from its own filings as carried in Metal Pilot’s company data.

Table 5. Peer positioning — quality metrics

Company Listing Project (interest) Stage Nickel reserve / resource Unit cost Jurisdiction
Canada Nickel TSXV:CNC Crawford (100%) Feasibility P&P 3,789 kt at 0.22% Net AISC US$1.54/lb Ontario, Canada
Lifezone Metals NYSE:LZM Kabanga (84%) Feasibility P&P 1,911.84 Mlb (867 kt) at 1.98% n/d Tanzania
Centaurus Metals ASX:CTM Jaguar (100%) Development P&P 459.2 kt at 0.73% n/d Pará, Brazil
EV Nickel TSXV:EVNI CarLang A (100%) PEA (May 2025) Indicated 510 Mt at 0.25%; no reserve Net AISC US$4.87/lb (PEA) Ontario, Canada
Talon Metals TSX:TLO Tamarack (51%) Pre-feasibility M&I 148 kt at 1.73%; no reserve n/d Minnesota, US

Source: Canada Nickel per Tables 3 and 4; peers per their own filings as carried in Metal Pilot’s company data — Lifezone 2025 Form 20-F (reserve, 18 Jul 2025), Centaurus 2024 Annual Report (31 Dec 2024), EV Nickel 2025 MD&A and May 2025 PEA, Talon resource estimate of 10 Oct 2022. Quality metrics only.

Crawford’s reserve is the largest in the set by more than four times, and its study cost the lowest, but its grade is the lowest of the five: it trades grade for scale and by-products.

3. Financials & balance sheet

Canada Nickel reports in Canadian dollars under IFRS with a 31 October year-end. As a developer it has no revenue, EBITDA or operating margin; the lines that matter are the cash it spends, the debt that funds it and the shares it issues. The Financial Metrics guide explains each line.

Table 6. Five-year financial summary (CA$m unless stated)

Line FY2021 FY2022 FY2023 FY2024 FY2025 9M FY2026
Revenue nil nil nil nil nil nil
YoY % n/a n/a n/a n/a n/a n/a
Cash margin n/a n/a n/a n/a n/a n/a
Net loss (6.4) (5.5) (14.2) (3.2) (26.2) (20.5)
EPS (C$) (0.08) (0.05) (0.11) (0.02) (0.13) (0.09)
Operating cash flow (6.3) (1.9) (7.4) (14.8) (5.0) (10.7)
Capex — exploration and evaluation (growth) (19.4) (49.3) (37.2) (56.7) (45.4) (24.8)
FCF (25.7) (51.2) (44.6) (71.5) (50.4) (35.5)
Net debt (bridge loans less cash) (3.3) 0.3 2.2 16.8 27.8 40.0
ND/EBITDA n/a n/a n/a n/a n/a n/a
Weighted average shares (m) 83.9 103.7 131.2 170.8 197.3 236.5
DPS nil nil nil nil nil nil

Source: Canada Nickel’s FY2025, FY2024, FY2023 and FY2022 audited financial statements and Q3 2026 condensed interim statements (investors, SEDAR+). FCF = operating cash flow + exploration and evaluation spending. FY2025 and the nine months come from the statements that report them, FY2024 to FY2021 from the following year’s comparative column. FY2021 net debt is net cash: no loan was outstanding at 31 October 2021. The convertible note is excluded from net debt here and carried at face in Section 7.

Earnings and cash. Losses swing with non-cash items — FY2024’s C$3.2 m loss against C$14.8 m of operating cash burn — so cash flow, not net income, is the line to read. Spending on Crawford’s studies and permits ran C$37–57 m a year from FY2022 to FY2025, after C$19.4 m in FY2021 and is all growth capex; there is no sustaining capital before production.

The cost deck. The study guides net C1 of US$0.39/lb and net AISC of US$1.54/lb in real 2023 US dollars, on a head grade of 0.26% in Phase 1, 0.24% in Phase 2 and 0.17% in Phase 3. The price-linked lines are the 2% royalty, the net profits interest (assumed bought down to 2.5%) and an assumed impact benefit agreement — US$1,990 m together, 4.1% of net smelter return; the tax shield from resource pools is in the deferred tax note, but the pool balances are n/d.

Net debt and liquidity. At 31 July 2026 cash was C$8.1 m against C$48.1 m of bridge loans and a C$12.5 m convertible note carried below its C$20 m face; the working-capital deficit of C$47.4 m puts a going-concern note on the statements. The Auramet loan (US$32 m) was extended to 9 November 2026 at 1.25% a month with 5.5 m warrants at C$1.52; its covenants are described only as customary. The August 2026 placement raised C$21.0 m at C$1.50. The rehabilitation provision is C$1.7 m. No facility is committed: the US$600 m investment-tax-credit facility is proposed.

Hedge book. Unhedged — no derivative instruments in the statements; a 5% move in the US dollar changes pre-tax results by about C$1.5 m through the US$ bridge loan.

Capital returns and shares. No dividend or buyback. Basic shares were 258,799,171 on 16 September 2026, with 32.3 m warrants, 13.5 m options and 5.9 m restricted share units outstanding; the Taykwa Tagamou Nation note converts into 16.67 m shares at C$1.20. Weighted shares rose 50% from FY2023 to FY2025.

4. Management, strategy & structure

4.1 Management & governance

Mark Selby, previously CEO of Royal Nickel Corporation, is CEO and a director; Wendy Kaufman (CPA, CA) is CFO. The chair is David Smith, formerly Senior Vice President Finance and CFO of Agnico Eagle Mines. The board has eight named directors: David Smith, Mark Selby, F. Quinn, Chief B. Archibald of the Taykwa Tagamou Nation, Jackie Przybylowski, J. Ovens, J. Morais and K. S. Gill. The only committee named in the filings on hand is the Audit Committee, of directors not involved in operations; independence, tenure and the other committees are n/d, because the 2026 management information circular is not in the source set. Related-party transactions are key-management compensation (Q3 2026 statements, Note 15).

4.2 Strategy

The strategy is to build Crawford first and then the district around it, on published resources at nine properties. The funding plan is US$2.5 billion — US$1 billion of equity and US$1.5 billion of debt — with a proposed US$600 m tax-credit facility through SB1 Markets. Offtake work includes the Samsung SDI option and a memorandum of understanding signed on 6 July 2026 between NetZero Metals and RWEST, aiming at a definitive agreement by the end of 2026; it is not a completed offtake. Targets: construction from Q4 2027 and first production in Q4 2029.

4.3 Ownership & structure

The October 2026 presentation shows four strategic holders at 11 August 2026: Agnico Eagle 8.7%, Samsung SDI 6.0%, Anglo American 5.3% and the Taykwa Tagamou Nation 6.1% on conversion. Agnico Eagle holds pro-rata participation and board nomination rights; Anglo American subscribed under an investor rights agreement of 8 February 2023. The company acquired Crawford in 2020 and earned 80% of Mann, now held through East Timmins Nickel, where the 20% minority sits at C$2.5 m. Shares: 258.8 m basic and 298.0 m diluted on the treasury method at 16 September 2026; the company’s fully diluted count is 327.2 m.

5. ESG & sustainability

The licence to operate rests on two First Nations agreements. The Taykwa Tagamou Nation invested C$20 m in the company, and the Wabun Tribal Council signed an infrastructure contracting agreement; the impact benefit agreements are still to finalise. Crawford’s study books US$891 m of carbon revenue over the life, and the FEED update’s CCUS case lifts NPV to US$2.9 bn. The company published an ESG report on 6 October 2026, but it is not in the source set, so the safety rate, the reporting framework and decarbonisation targets are n/d.

6. Risks

Table 7. Risk register

Risk Type Likelihood / impact Exposure Mitigant
Funding gap and dilution Balance sheet / dilution High / High C$2,581 m gap, 1,018% of market cap; equity share raised at C$0.882 in Section 7 Strategic holders; debt and tax-credit facilities under negotiation
Bridge loan refinancing Balance sheet High / Medium US$32 m due 9 Nov 2026 at 1.25% a month; working-capital deficit C$47.4 m August placement C$21.0 m; equity access
Nickel price Commodity Medium / High Crawford NPV C$454 m at US$13,000/t against C$1,538 m at the base Low study AISC; long life
Iron and chromium prices Commodity Medium / High Iron 106% and chromium 71% of Crawford’s after-tax NPV; no chromium price series Two products sold at the mine gate
Permits and schedule Jurisdiction Medium / High Construction permits due Q3 2027; first production Q4 2029, two years after the study Federal Decision Statement in hand
Capital overrun Operational Medium / High FEED initial capital US$2,047 m vs the study’s US$1,943 m Phased build: Phase 1 at 60 kt/d
First Nations agreements ESG Low / Medium Impact benefit agreements not final TTN equity partner; Wabun agreement
USD/CAD Commodity Medium / Low ±10% moves NAV/share to C$1.47 / C$0.87 C$ costs, US$ revenue

Source: Sections 2–5 and Section 7 of this analysis, from Canada Nickel’s Q3 2026 filings and the Crawford technical report on SEDAR+.

Figure 5. Risk matrix — likelihood against impact

Impact if it happens
High
Medium
Low
Funding gap
Bridge loan
Nickel price
Iron, chromium
Permits, schedule
Capital overrun
First Nations
USD/CAD
Low
Medium
High
Likelihood over the next five years →

Source: Table 7. The shaded corner is high likelihood and high impact.

Section 7 prices the funding gap (the equity raise), the stage risk (the 0.50× row weight) and the by-product decks; the bridge loan sits in its net debt.

7. Valuation

Valuation as of 22 October 2026, in Canadian dollars. Horizon: spot fair value. Price deck: base nickel US$17,000/t, the representative of the trailing averages of the LME cash price — US$16,575 (3-month), US$17,347 (6-month) and US$16,729 (12-month) to September 2026 — snapped to a five-column US$13,000–21,000/t grid in US$2,000 steps, with every grid price run as a scenario (deep bear US$13,000 / bear US$15,000 / base US$17,000 / bull US$19,000 / deep bull US$21,000). Iron, Crawford’s largest by-product, runs on its own deck — iron ore US$100/t (62% Fe), from 3-, 6- and 12-month averages of US$97.40, US$101.28 and US$102.26/t (World Bank Pink Sheet, iron ore 62% Fe CFR, to September 2026), on a US$70–110/t grid — held at that price in every nickel scenario; chromium is held at the study’s US$1.75/lb because no chromium price series is on record, and cobalt, the platinum-group metals and the carbon credits stay at the study’s prices. Discount rate 10% real, after-tax — the base-metals rate for a small, single-asset company — sensitised 8–12%. Share price C$0.98 (TSXV close, 22 October 2026); 298.0 m shares diluted (258.8 m outstanding, 5.9 m restricted share units, and 33.4 m warrants and options whose exercise prices are not disclosed, counted in full; the 12.5 m warrants at C$1.52 and C$2.25 and the TTN convertible note at C$1.20 sit above the share price); balance sheet at 31 July 2026 with the August 2026 placement; the US$ deck converts at US$1 = C$1.4021 (22 October 2026).

Canada Nickel is valued as a developer: Crawford holds a 2023 feasibility study and, since 31 July 2026, its federal Decision Statement, while the provincial and federal construction permits are due in 2027 and the US$2.5 bn build is not yet funded. The method follows the How to Value Commodity Stocks guide. Crawford is rebuilt from the feasibility study’s own year-by-year production and cash-flow schedule, moved two years later to the company’s current first-production date of late 2029 and re-priced at each nickel price, and carries its stage risk in a row weight of 0.50×, so the discount rate stays at the convention. The funding gap is about ten times the market capitalisation, so the equity share of the company’s funding plan is raised at a 10% discount to the share price in every scenario, and the new shares enter the count. The developer’s transaction-comparison and EV-per-reserve methods have no filed nickel deal and no nickel anchor to stand on, so the second weighted method is a free-cash-flow yield on Crawford’s first full production year, discounted back to today. The driver line (Table 14) sums to +0.04, so the targets move off their anchors to 1.04× P/NAV and a 6.7% FCF yield.

Table 8. Load-bearing inputs — the filed figures the valuation moves on (full register: Table 23)

Input Value Where §7 uses it Source
Crawford — Canada Nickel interest 100% Table 11, blocks 1–2 Filed · Q3 2026 MD&A · Description of The Business · “Company acquired 100 per cent of the Crawford Nickel Sulphide Project” · p.3
Crawford Proven + Probable reserve (100%) 1,715 Mt at 0.22% Ni; 3,789 kt Ni Table 11, block 2 — resource conversion Filed · Crawford technical report (FS) · Table 1-9 · “Proven + Probable” · p.59
Crawford Measured + Indicated, East + Main-West, inclusive 2,363.0 kt + 3,672.3 kt Ni Table 11, block 2 Filed · Crawford technical report (FS) · Table 1-7 · “Measured + Indicated” · p.58
Crawford payable metal, life of mine 3,130 Mlb Ni; 4,961 Mlb NiEq Table 11, block 1 — volume Filed · Crawford technical report (FS) · Table 1-14 · “Payable Ni” · p.74
Crawford schedule by year — payable metal, site costs, royalties, capital, taxes (technical report Table 22-3) site costs US$18,661 M over the life Table 11, lines 1–10 Filed · Crawford technical report (FS) · Table 22-3 · “Site Costs” · p.538
Crawford study exchange rate C$1.00 = US$0.76 Table 11, block 1 — C$ costs Filed · Crawford technical report (FS) · Table 1-12 · “Costs shown in US dollars have been converted at an exchange rate of” · p.72
Crawford capital — initial, expansion, sustaining, closure C$2,556 M · C$2,105 M · C$1,950 M · C$175 M Table 11, block 1 — capital Filed · Crawford technical report (FS) · Table 1-12 · “Total Capital” · p.72
Crawford construction start and first production Q4 2027 · Q4 2029 Table 11, block 1 — timing Filed · Investor presentation October 2026 · Federal approval received — timeline · “Construction start” · p.19
Statutory income tax rate 26.5% Table 11 line 8 — marginal rate, 33.0% with the 8.88% mining-tax ratio Filed · FY2025 audited FS · Note 18 · “combined Canadian federal and provincial statutory income tax rate of 26.5%" · p.40
Cash / bridge loans, 31 Jul 2026 C$8,066,449 / C$48,069,578 Table 13 — net debt Filed · Q3 2026 interim FS · Condensed Interim Consolidated Statements of Financial Position · “Cash and cash equivalents” · p.2
Crawford funding plan US$2.5B: equity US$1B, debt US$1.5B Table 13 — the equity raise Filed · Investor presentation October 2026 · Funding plan · “Funding Plan” · p.18
Shares, diluted basis 298,020,490 Table 13 — per share Derived · 258,799,171 basic + 5,861,053 RSUs + 13,516,134 options + 19,844,132 warrants (32,344,132 less 7,000,000 at $2.25 and 5,500,000 at $1.52, out of the money); the TTN convertible at $1.20 out of the money, at face
Nickel, LME cash — 3-, 6-, 12-month averages US$16,575 · US$17,347 · US$16,729/t Figure 7, Table 18 — deck Market · World Bank Pink Sheet monthly · “Nickel ($/mt)” · Jul–Sep, Apr–Sep 2026 and Oct 2025–Sep 2026 (Market/worldbank_pinksheet_monthly_20261006.xlsx)
Iron ore, 62% Fe CFR — 3-, 6-, 12-month averages US$97.40 · US$101.28 · US$102.26/t Table 11 line 2 — iron credit; secondary decks Market · World Bank Pink Sheet monthly · iron ore, 62% Fe CFR · Jul–Sep, Apr–Sep 2026 and Oct 2025–Sep 2026 (Market/worldbank_pinksheet_monthly_20261006.xlsx)

Source: each row’s filing as cited — Canada Nickel’s Q3 2026 and FY2025 filings and the Crawford technical report and SEDAR+; deck rows per the World Bank Pink Sheet monthly nickel series.

Metal Pilot Premium

Valuation workings — Premium

The workings behind this valuation — the method, the models, the sensitivity grids and the scenarios, 11 tables and 3 figures in all — are for Metal Pilot Premium members.

  • 7.1 Method selection
  • 7.2 Net asset value
  • 7.3 Relative valuation
  • 7.4 Further weighted methods
  • 7.5 Cross-checks
  • 7.6 Scenarios & fair value

Want to see one first? These valuations are open to every reader: BHP Group (BHP), Cameco (CCJ), ExxonMobil (XOM), Newmont (NEM) and Wheaton Precious Metals (WPM).

Create a Metal Pilot accountLog in

See Premium plansRead a free example

You are signed in, and your plan does not include valuation workings. They come with Metal Pilot Premium.

Upgrade to Premium

The premium section could not be loaded right now.

Premium — unlocked

8. Near-term catalysts (1–3 years)

Table 20. Near-term catalysts

Catalyst Timing Why it matters
Auramet bridge loan repaid or refinanced 9 Nov 2026 Clears the nearest maturity behind the going-concern note
NetZero Metals–RWEST definitive agreement End of 2026 (targeted) Turns a memorandum into a contracted offtake
Investment-tax-credit facility, up to US$600 m n/d (proposed) Lowers the equity share of the build
Provincial and federal construction permits Q3 2027 Moves Crawford toward the permitted 0.60× row
Crawford project financing — US$1.5 bn debt, US$1 bn equity Before construction, Q4 2027 Sets the dilution Section 7 assumes at C$0.882
Construction start Q4 2027 Starts the 27-month build to first production in Q4 2029

Source: Canada Nickel’s Q3 2026 MD&A and condensed interim statements and the October 2026 investor presentation (timeline, funding plan).

8.1 Takeover optionality

Crawford is the kind of asset a major buys rather than builds: a reserve of 3,789 kt of nickel with a 41-year plan in Ontario, past its federal approval. Against that sit a US$2.5 billion build, a 0.22% grade and a mine whose payable value is 36.9% by-products, which narrows the field to buyers that sell iron and chromium as well as nickel. Three of the four strategic holders have a contractual link, which is the only evidence this analysis admits for a buyer.

Table 21. Takeover case

Element Read
Target case 3,789 kt Ni proven + probable, 41 years, federal Decision Statement in hand, Ontario
Disqualifiers US$2.5 bn to build; 0.22% Ni grade; 36.9% of payable value in by-products
Holders with a sourced link Agnico Eagle (8.7%; pro-rata and board nomination rights) · Anglo American (5.3%; investor rights agreement, 8 Feb 2023) · Samsung SDI (6.0%; option on 10% of Crawford for US$100 m)
Effect on the verdict None — no bid is in the value; a sale to a strategic holder would replace the equity raise Section 7 assumes

Source: Canada Nickel’s FY2025 audited financial statements (Note 8), FY2024 MD&A and the October 2026 investor presentation; holdings at 11 Aug 2026.

9. Rating & verdict

Figure 9. Scorecard by dimension, 22 October 2026

Balance sheet★15%
Management★★★15%
Assets & scale★★★★15%
Reserves & life★★★★★15%
Cost & margins★★★★8%
Growth★★★★8%
Capital allocation★★8%
Jurisdiction★★★★8%
ESG★★★8%
Score by dimension Weighted composite ★★★½ (3.31)
Each ring is one star; the outer ring is ★★★★★. Weights in Table 22.

Figure data: Table 22. Each spoke prints its stars and weight; the dashed ring is the weighted composite, 3.31/5.

Table 22. Scorecard rationale — Canada Nickel, 22 October 2026

Dimension Weight Score Rationale
5. Balance sheet & funding gap 15% ★ Cash C$8.1 m against C$48.1 m of bridge loans and a C$47.4 m working-capital deficit, with a going-concern note and the US$32 m Auramet loan due 9 Nov 2026; the C$2,581 m gap is 1,018% of market capitalisation — a red flag on any peer basis (Q3 2026 FS, 31 Jul 2026).
7. Management & governance 15% ★★★ The CEO ran Royal Nickel and the chair was Agnico Eagle’s CFO; three strategic holders carry investor rights; independence, tenure and committees beyond Audit are not on hand — the peer median on what is known (October 2026 presentation).
1. Asset quality & scale 15% ★★★★ 3,789 kt Ni proven + probable, more than four times Lifezone’s 867 kt at Kabanga, the next largest; but the lowest grade in the set, 0.22% against Centaurus’s 0.73% and Lifezone’s 1.98%, and one asset (technical report, eff. 31 Aug 2023; Table 5).
3. Reserves, life & replacement 15% ★★★★★ 1,715 Mt proven + probable supports a 41-year plan, twice EV Nickel’s 20-year PEA life; 6,035 kt Ni measured and indicated at Crawford and 10.3 Mt across the district (technical report; Q3 2026 MD&A; Table 5).
2. Cost position & margins 8% ★★★★ Study estimate: net AISC US$1.54/lb, an 80.0% margin at US$17,000/t, against EV Nickel’s US$4.87/lb PEA; it rests on US$5.57/lb of by-product credits (technical report Table 1-14; Table 5).
4. Growth & optionality 8% ★★★★ Phase 2 doubles throughput to 120 kt/d; the district adds 10.3 Mt Ni measured and indicated and 13.2 Mt inferred with no study — more unvalued resource than any peer’s whole reserve (Q3 2026 MD&A).
6. Capital allocation & returns 8% ★★ No dividend or buyback; weighted shares up 50% from FY2023 to FY2025 and bridge debt at 1.25% a month to carry the studies; peer dilution figures are not on hand, so the score rests on the company’s own record (FY2025 FS; Q3 2026 FS Note 19).
8. Jurisdiction & geopolitics 8% ★★★★ Ontario with the federal Decision Statement (31 Jul 2026) and construction permits due Q3 2027 — the jurisdiction of EV Nickel’s CarLang, ahead of Lifezone’s Tanzania and Centaurus’s Brazil (Q3 2026 MD&A; Table 5).
9. ESG & licence to operate 8% ★★★ Taykwa Tagamou Nation C$20 m equity and the Wabun agreement, impact benefit agreements still open; safety and framework data not in the source set, nor peer ESG data, so the score rests on the company’s own record (Q3 2026 MD&A; release of 6 Oct 2026).
Composite 100% ★★★½ Solid

Source: as cited per row — Canada Nickel’s Q3 2026 filings and the Crawford technical report on SEDAR+; peers per Table 5. Every score is relative to the peer set declared in Section 2.6.

The arithmetic: 0.15 × (1 + 3 + 4 + 5) + 0.08 × (4 + 4 + 2 + 4 + 3) = 1.95 + 1.36 = 3.31/5 → ★★★½ Solid. Developer weights put the balance sheet, management, the asset and the reserve at 15% each and the other five at 8%.

The two-axis verdict: Solid (★★★½) and Modestly undervalued (wide band), implied +19.2%, as of 22 October 2026 → re-rating candidate — the catalyst is the Crawford financing package.

The two axes answer different questions. The quality score rests on a reserve and a jurisdiction no financing changes; the value read rests on the stage weight and the price of the equity raise, which the next year of news will move.

The shares price in a market-implied nickel deck of ~US$15,672/t, below the 12-month average of US$16,729/t; the target multiples carry Dimensions 1, 2, 3, 5, 6 and 8 (+0.04). Bull: the package closes with less equity or at a higher price, and nickel holds above ~US$17,742/t, where the read turns Undervalued. Bear: a deeper discount, a permit slip, or nickel below ~US$16,362/t turns it Fairly valued. To rank Canada Nickel against every listed nickel name, screen the sector on Metal Pilot’s nickel mining stock screener.

10. Sources, methodology & disclaimer

10.1 Sources, methodology & data vintage

Company filings. Canada Nickel’s Q3 2026 condensed interim financial statements and MD&A (balance sheet, debt, shares, approvals), the FY2025 and FY2024 audited financial statements and MD&As, the FY2023 and FY2022 audited financial statements, the October 2026 investor presentation and the releases of 31 July and 6 October 2026, from canadanickel.com and SEDAR+.

Technical basis. The Crawford NI 43-101 feasibility technical report (effective 1 October 2023, November 2024 revision; reserves effective 31 August 2023), including its year-by-year production and cash-flow schedule; the Bannockburn and Midlothian resource reports; the 2025 FEED metrics as reported in the FY2025 MD&A.

Market and peer data. Share price C$0.98 at the 22 October 2026 TSXV close per Yahoo Finance; USD/CAD 1.4021 per the Bank of Canada; nickel and iron ore monthly averages from the World Bank Pink Sheet to September 2026; peers from their filings as carried in Metal Pilot’s company data (Table 5).

Methodology. Archetype: developer. The scorecard uses the developer weights against four peers. The valuation blends risked P/NAV (55%) and FCF-yield support (45%) on a base nickel deck of US$17,000/t — the representative trailing average on the US$13,000–21,000/t grid, with every grid price run as a scenario — and iron ore at US$100/t, at 10% real; the consensus target is a 0% cross-check. Data as of 22 October 2026; refreshed on each permitting, financing or construction milestone.

Re-run log. 23 October 2026: first publication — a new analysis on the current template; at C$0.98 the fair value is C$1.17, implied +19.2%, Modestly undervalued (wide band); quality 3.3/5 Solid. 23 October 2026, pre-publication review: the iron-ore deck’s source and date, the Figure 7 notes, the funding and FCF-yield workings’ notes, a seventh gap (the Mann minority) and two Table 6 cells added; NAV/share C$1.17, fair value C$1.17, implied +19.2% and the read unchanged.

Omitted figures and data gaps. The asset map, a Section 3 financial chart (no revenue) and a Section 5 safety trend (no safety data on hand) are not built. Not in the source set: the 2026 management information circular (board independence and committees), the 2025 ESG report (safety, framework), an analyst-consensus capture, the Reid, Mann and Texmont resource rows, the royalty holders’ names and a chromium price series. The model’s full printout — P/NAV map, deck sensitivity, cross-checks, secondary decks and the nickel × iron ore grid — is claude/valuation-models/canada-nickel-cnc.out.md.

Table 23. Source register — the filed figures behind the valuation (load-bearing inputs: Table 8)

InputValueAs ofWhere §7 uses itSource
Management's discussion and analysis, nine months ended 31 July 2026 (dated 16 Sep 2026)
Crawford — interest100% (acquired 2020)31 Jul 2026asset register; operator CNC; Canada (Ontario)Filed · Q3 2026 MD&A · Description of The Business · "Company acquired 100 per cent of the Crawford Nickel Sulphide Project" · p.3
Crawford — federal approval in handpositive Decision Statement, 31 Jul 2026 (Impact Assessment Act)31 Jul 2026approvals in handFiled · Q3 2026 MD&A · Key developments · "received a positive Decision Statement" · p.4
Crawford — construction timingplanned construction targeted for late 202731 Jul 2026schedule; approvals outstanding (provincial and federal permits)Filed · Q3 2026 MD&A · Key developments · "required ahead of planned construction targeted for late 2027" · p.5
ITC monetisation facility (proposed)up to US$600 M via SB1 Markets — not a completed financing31 Jul 2026funding — not in handFiled · Q3 2026 MD&A · Financing · "not currently a completed financing" · p.5
Timmins district — nine published MREsM&I 4.36 Bt at 0.24% Ni (10.3 Mt Ni); Inferred 5.7 Bt at 0.23% (13.2 Mt)31 Jul 2026resources by deposit (total)Filed · Q3 2026 MD&A · Unlocking Timmins Nickel District · "published mineral resource estimates for nine of its properties" · p.6
Nesbitt MRE (100%)Indicated 24.5 Mt at 0.23% Ni (57,500 t); Inferred 152.1 Mt at 0.23% (351,000 t)23 Jul 2026resources by depositFiled · Q3 2026 MD&A · Nesbitt · "Indicated Resources total 24.5 million tonnes" · p.7
Deloro MRE (100%)Indicated 119 Mt at 0.25% Ni (300,000 t); Inferred 498 Mt at 0.25% (1.25 Mt)23 Jul 2026resources by depositFiled · Q3 2026 MD&A · Deloro · "Indicated Resources now total 119 million tonnes" · p.7
Common shares outstanding at MD&A date258,799,171 shares; 32,344,132 warrants; 13,516,134 options; 5,861,053 RSUs16 Sep 2026basic count; dilutive securitiesFiled · Q3 2026 MD&A · Share capital · "common shares issued" · p.22
ListingsTSXV:CNC since 27 Feb 2020; OTCQX:CNIKF31 Jul 2026§1 identityFiled · Q3 2026 MD&A · Description of The Business · "commenced trading on the TSX Venture Exchange" · p.3
NetZero Metals — RWEST MOUMOU 6 Jul 2026; definitive agreement targeted end-2026; not a completed offtake31 Jul 2026§4 offtakesFiled · Q3 2026 MD&A · Financing · "The MOU does not represent a completed offtake agreement" · p.5
Indigenous agreementsTTN $20 M equity; Wabun Tribal Council infrastructure contracting agreement; IBA/MSA to finalise31 Jul 2026§4 ESG — communityFiled · Q3 2026 MD&A · Key developments · "major infrastructure contracting agreement with Wabun Tribal Council" · p.5
CNC investor presentation, October 2026
Crawford — permits outstandingprovincial/federal construction permits Q3 2027; provincial operating permits Q2 2029Oct 2026approvals outstandingFiled · Investor presentation October 2026 · Federal approval received — timeline · "Provincial, federal permits required for construction" · p.19
Crawford — scheduleconstruction start Q4 2027 (27-month build); first production Q4 2029Oct 2026first-production date; ramp startFiled · Investor presentation October 2026 · Federal approval received — timeline · "Construction start" · p.19
Crawford funding planUS$2.5B: equity US$1B, debt US$1.5BOct 2026remaining capital; funding riskFiled · Investor presentation October 2026 · Funding plan · "Funding Plan" · p.18
Samsung SDI optionUS$100 M for a 10% direct interest in Crawford; LOM nickel offtakeOct 2026stream/offtake terms; implied project valueFiled · Investor presentation October 2026 · Strong shareholder support · "Option to acquire a 10% direct interest" · p.17
CEOMark Selby — CEO; previous CEO of Royal Nickel CorporationOct 2026§4 leadershipFiled · Investor presentation October 2026 · Management · "Mark Selby, CEO" · p.14
ChairDavid Smith — Chair; former Senior VP Finance and CFO of Agnico Eagle MinesOct 2026§4 boardFiled · Investor presentation October 2026 · Board · "David Smith, Chair" · p.14
Strategic shareholders8.7% (gold major — Agnico Eagle) · 6.0% (Samsung SDI) · 5.3% (diversified major — Anglo American) · 6.1% (TTN, on conversion)11 Aug 2026§4 ownership — holders as the October 2026 presentation shows them (p.17; names on p.3 and p.28)Filed · Investor presentation October 2026 · Strong shareholder support · "Strong Shareholder Support" · p.17
NI 43-101 Technical Report and Feasibility Study, Crawford (effective 1 Oct 2023; Nov 2024 revision)
Crawford Proven + Probable Mineral Reserves1,715 Mt at 0.22% Ni, 0.013% Co; 3,789 kt Ni, 215 kt Co contained31 Aug 2023reserves table; NAV volume basisFiled · Crawford technical report (FS) · Table 1-9 · "Proven + Probable" · p.59
Crawford Proven reserves994 Mt at 0.24% Ni; 2,345 kt Ni31 Aug 2023reserves by categoryFiled · Crawford technical report (FS) · Table 1-9 · "Proven" · p.59
Crawford Probable reserves721 Mt at 0.20% Ni; 1,444 kt Ni31 Aug 2023reserves by categoryFiled · Crawford technical report (FS) · Table 1-9 · "Probable" · p.59
Crawford East Zone resources (inclusive)M+I 1,034.6 Mt at 0.23% Ni (2,363.0 kt Ni); Inferred 157.3 Mt at 0.23% (367.1 kt)31 Aug 2023resources by depositFiled · Crawford technical report (FS) · Table 1-7 · "Measured + Indicated" · p.58
Crawford Main-West Zone resources (inclusive)M+I 1,527.2 Mt at 0.24% Ni (3,672.3 kt Ni); Inferred 1,535.8 Mt at 0.22% (3,359.2 kt)31 Aug 2023resources by depositFiled · Crawford technical report (FS) · Table 1-8 · "Measured + Indicated" · p.58
Crawford BFS post-tax NPV8% / IRRUS$2,475 M · 17.1%1 Oct 2023Table 8 study NPVFiled · Crawford technical report (FS) · Table 1-14 · "Post-Tax NPV8%" · p.74
Crawford BFS net C1 / net AISCUS$0.39/lb Ni · US$1.54/lb Ni1 Oct 2023unit costFiled · Crawford technical report (FS) · Table 1-14 · "Net AISC" · p.74
Crawford BFS payable metal, LOM3,130 Mlb Ni payable; 4,961 Mlb NiEq1 Oct 2023LOM volume; average = Derived over the life rowFiled · Crawford technical report (FS) · Table 1-14 · "Payable Ni" · p.74
Crawford BFS phasesPhase 1 42 months at 60 kt/d; Phase 2 26½ years and Phase 3 11¼ years at 120 kt/d1 Oct 2023life basis (≈41 years of milling)Filed · Crawford technical report (FS) · Section 1.21 · "Phase 2 covers the following" · p.73
Crawford BFS capital (C$M)initial C$2,556; expansion C$2,105; sustaining C$1,950; total C$6,611 (US$5,024); closure C$1751 Oct 2023remaining capitalFiled · Crawford technical report (FS) · Table 1-12 · "Total Capital" · p.72
Crawford BFS exchange rateC$1.00 = US$0.761 Oct 2023study FXFiled · Crawford technical report (FS) · Table 1-12 · "Costs shown in US dollars have been converted at an exchange rate of" · p.72
Crawford BFS schedule — site costsUS$M: Total 18,661 · Constr. – · Yr 1 336 · Yr 2 367 · Yr 3 367 · Yr 4 454 · Yr 5 579 · Yr 6 623 · Yr 7 613 · Yr 8 612 · Yr 9 594 · Yr 10 595 · Yr 11 625 · Yr 12 599 · Yr 13 605 · Yr 14 581 · Yr 15 590 · Yr 16 655 · Yr 17 569 · Yr 18 560 · Yr 19 548 · Yr 20 521 · Yr 21–30 4,608 · Yr 30–41 3,0601 Oct 2023Table 11 line 5 — site costs by yearFiled · Crawford technical report (FS) · Table 22-3 · "Site Costs" · p.538
Crawford BFS — Year 1 of the schedulefirst full year of production 2028; one price in 2023 real terms for all years1 Oct 2023schedule year 1 — re-dated to FY2030 for the company's current first production, Q4 2029Filed · Crawford technical report (FS) · Section 19.2 · "The first full year of production from Crawford is planned for" · p.454
Crawford BFS — nickel price and payabilityNi concentrate US$21,000/t (US$9.53/lb), 91% payable; Ni-Fe concentrate US$21,000/t, 91% payable1 Oct 2023deck — nickel (2023 long-term real)Filed · Crawford technical report (FS) · Table 19-1 · "Ni Concentrate" · p.454
Crawford BFS — chromium price and payabilityUS$1.75/lb, 65% payable1 Oct 2023by-product deck — chromiumFiled · Crawford technical report (FS) · Table 19-1 · "Chromium" · p.454
Crawford BFS — iron concentrate equivalent priceUS$89/t iron ore concentrate equivalent (scrap US$325/t at 50% payability)1 Oct 2023by-product deck — iron, concentrate formFiled · Crawford technical report (FS) · Section 22.3 · "An equivalent long-term price for iron ore concentrate of" · p.533
Crawford — NSR royalty2% NSR on the patented lands transferred from Noble (Noble bought the 5% NSR in Dec 2019); holder not named1 Oct 2023royalty terms — holder n/dFiled · Crawford technical report (FS) · Section 4.4 · "those patented properties are now subject to a 2% NSR" · p.102
Crawford — net profits interest5% NPI held by a third party (not named), payable from commercial production on net profits after capital, operating costs, royalties and the IBA; up to 2.5% repurchasable at C$0.8 M per 1% (C$2 M for 2.5%)1 Oct 2023royalty terms — holder n/dFiled · Crawford technical report (FS) · Section 4.4 · "A third party holds the rights to receive a 5% interest in the net profits" · p.102
Crawford BFS — royalties in the cash flowexisting 2% NSR; an assumed IBA (not yet negotiated); the 5% NPI, assumed bought down to 2.5% for C$2 M1 Oct 2023Table 11 line 6 — royalties ('Royalties, etc.')Filed · Crawford technical report (FS) · Section 22.3 · "existing 2% NSR royalty" · p.533
Management's discussion and analysis, year ended 31 October 2025
Crawford FEED post-tax NPV8% / IRRUS$2,810 M · 17.6%31 Oct 2025Table 3 study parameters; a 0% cross-check (no technical report)Filed · FY2025 MD&A · Updated engineering and project metrics · "Net Present Value (at 8%)" · p.5
Crawford FEED initial / total capitalUS$2,047 M · US$5,724 M31 Oct 2025remaining capital (FEED basis)Filed · FY2025 MD&A · Updated engineering and project metrics · "Initial Capital Cost" · p.5
Mann — interest80% (earn-in completed; now held via East Timmins Nickel)31 Oct 2025asset register; NCIFiled · FY2025 MD&A · Mann · "Canada Nickel currently owns 80% of the Mann Project" · p.10
Condensed interim consolidated financial statements, 31 July 2026
Regional properties — vendor NSRsNSR 1–2%; CNC may buy back 50% for $500,000 (1%) or $1 million (2%)31 Jul 2026royalty terms (regional only); Crawford's royalties in the technical-report rowsFiled · Q3 2026 interim FS · Note 4 · "net smelter royalty" · p.8
Cash and cash equivalents, 31 Jul 2026C$8,066,44931 Jul 2026balance-sheet face; bridgeFiled · Q3 2026 interim FS · Condensed Interim Consolidated Statements of Financial Position · "Cash and cash equivalents" · p.2
Bridge loan facilities, 31 Jul 2026C$48,069,57831 Jul 2026balance-sheet face; bridgeFiled · Q3 2026 interim FS · Condensed Interim Consolidated Statements of Financial Position · "Bridge loan facilities" · p.2
Convertible note, 31 Jul 2026C$12,535,65631 Jul 2026balance-sheet face; bridgeFiled · Q3 2026 interim FS · Condensed Interim Consolidated Statements of Financial Position · "Convertible note" · p.2
Asset retirement obligation, 31 Jul 2026C$1,661,46231 Jul 2026balance-sheet face; bridgeFiled · Q3 2026 interim FS · Condensed Interim Consolidated Statements of Financial Position · "Asset retirement obligation" · p.2
Non-controlling interest, 31 Jul 2026C$2,520,88731 Jul 2026balance-sheet face; bridgeFiled · Q3 2026 interim FS · Condensed Interim Consolidated Statements of Financial Position · "Non-controlling interest" · p.2
Working capital deficit (going concern)C$47,418,35031 Jul 2026liquidity; going-concern noteFiled · Q3 2026 interim FS · Note 1 · "working capital deficit balance" · p.6
Auramet loan — extended maturity and ratedue 9 Nov 2026; 1.25% per month; 5,500,000 warrants at $1.5228 Jul 2026maturities; cost of debtFiled · Q3 2026 interim FS · Note 19 — Subsequent events · "extended the repayment date of its Auramet Inc." · p.29
TTN convertible note — terms$20 M face; converts into 16.67 M shares at $1.20; five-year term; coupon 4.65%31 Jul 2026convertibles at face; diluted countFiled · Q3 2026 interim FS · Note 7 · "TTN invested $20 million in the Note" · p.14
August 2026 private placement14,000,000 units at $1.50 = $21,000,000; half-warrant at $2.25 for 36 months31 Jul 2026cash since 31 Jul; sharesFiled · Q3 2026 interim FS · Note 19 — Subsequent events · "August 2026 Private Placement" · p.29
NI 43-101 MRE technical report, Bannockburn (issued 2 Feb 2026)
Bannockburn MREIndicated 63.2 Mt at 0.28% Ni (179.7 kt); Inferred 129.0 Mt at 0.27% (342.9 kt)2 Feb 2026resources by depositFiled · Bannockburn technical report · Table 14-9 · "Indicated" · p.145
NI 43-101 MRE technical report, Midlothian (resource effective 15 Dec 2025)
Midlothian MREInferred 595.3 Mt at 0.28% Ni (1,683.8 kt)15 Dec 2025resources by depositFiled · Midlothian technical report · Table 1-2 · "Inferred" · p.25
Audited consolidated financial statements, year ended 31 October 2025
Statutory tax rate26.5%31 Oct 2025tax basisFiled · FY2025 audited FS · Note 18 · "combined Canadian federal and provincial statutory income tax rate of 26.5%" · p.40
Derived
Crawford BFS — payable value by product at the study deck, LOMCo US$580.5 M · Pd US$380.7 M · Pt US$98.9 M · Fe US$9,425.0 M · Cr US$6,928.3 M = by-products US$17,413.3 M; Ni US$29,828.9 M; metal total US$47,242.2 M → by-products 36.9% of payable metal value; implied 4,957.2 Mlb NiEq vs 4,961 Mlb filed1 Oct 2023secondary-commodity tiers (share of payable value) and the by-product deck rowsDerived · payable LOM of cobalt, palladium, platinum, iron, chromium and nickel (Table 22-3) × Table 19-1 price (nickel at US$9.53/lb); revenue is printed by concentrate only, not by product
Crawford BFS — by-product credits inside the net C1 and the net AISC, LOMcredits US$17,440.3 M (US$5.57/lb Ni) = site costs US$18,661 M − net C1 US$0.39/lb × 3,130 Mlb payable Ni; metal credits at the study deck US$17,413.3 M (by-product row above; −0.2%, rounding) — the identity closes without the US$891 M carbon revenue; net AISC rebuilt = net C1 US$1,220.7 M + royalties etc. US$1,990 M + sustaining US$1,481 M + W/C and closure US$134 M = US$4,825.7 M → US$1.54/lb (filed 1.54)1 Oct 2023the credits held in the net AISC, split by product for the secondary decksDerived · Table 22-3 site costs, royalties etc., sustaining capital, W/C and closure, and Table 1-14 net C1, net AISC, payable Ni; Table 22-2 note 2: "Net of byproduct credits"
Shares, diluted — the model's count (treasury / if-converted)298,020,49016 Sep 2026Table 13 — per shareDerived · 258,799,171 basic + 5,861,053 RSUs + 13,516,134 options + 19,844,132 warrants (32,344,132 less 7,000,000 at $2.25 and 5,500,000 at $1.52, out of the money); the TTN convertible at $1.20 out of the money, at face
Market
FX USD/CADUS$1.00 = C$1.402122 Oct 2026US$ study → C$Market · Bank of Canada · "FXUSDCAD" · 22 Oct 2026 (Market/boc_fxusdcad_20261015_20261023.csv)
Nickel, LME cash — 3-, 6-, 12-month averages to Sep 2026US$16,575 · US$17,347 · US$16,729/t30 Sep 2026deck — base US$17,000/t on the 13,000–21,000 gridMarket · World Bank Pink Sheet monthly · "Nickel ($/mt)" · Jul–Sep, Apr–Sep 2026 and Oct 2025–Sep 2026 (Market/worldbank_pinksheet_monthly_20261006.xlsx)
Nickel, LME cash — five-year average and monthly high / lowUS$19,456/t · US$33,924 (Mar 2022) / US$14,671 (Nov 2025)30 Sep 2026five-year test of the deck; market-implied deck readMarket · World Bank Pink Sheet monthly · "Nickel ($/mt)" · Oct 2021 – Sep 2026 (Market/worldbank_pinksheet_monthly_20261006.xlsx)
Iron ore, 62% Fe CFR — 3-, 6-, 12-month and five-year averages; monthly high / lowUS$97.40 · US$101.28 · US$102.26 · US$111.17/t; US$152.1 (Mar 2022) / US$92.3 (Jun 2025)30 Sep 2026iron deck — base US$100/t on the 70–110 grid; five-year testMarket · World Bank Pink Sheet monthly · "Iron ore, cfr spot ($/dmtu)" · Jul–Sep, Apr–Sep 2026, Oct 2025–Sep 2026 and Oct 2021–Sep 2026 (Market/worldbank_pinksheet_monthly_20261006.xlsx)

Source: each row’s document as cited — Canada Nickel’s filings and SEDAR+; deck rows per the World Bank Pink Sheet and the Bank of Canada. The load-bearing inputs that open Section 7 are Table 8.

10.2 Disclaimer & disclosure

This analysis is for information only and is not investment advice. It is a point-in-time snapshot as of 22 October 2026: the price, the valuation and the verdict move with the market and the nickel price, and a pre-production developer’s value swings on financing, permitting and construction news. Reserves and study economics are estimates, not results. The quality rating and value read are analytical judgements, not a recommendation to buy or sell. This report was prepared with AI assistance from primary filings; verify anything material before acting. The author holds no position in any company named.